Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
00:00:31,698 --> 00:00:34,333
Various standards are available
2
00:00:34,601 --> 00:00:38,337
detailing the requirements of the construction ot the equipment racks
3
00:00:38,605 --> 00:00:41,240
that are commonly used in a data center
4
00:00:41,241 --> 00:00:45,244
Most data centers use the traditional nineteen inch racks
5
00:00:45,245 --> 00:00:51,617
the outer width ot these racks matches the size of the raised access floor tile
6
00:00:51,618 --> 00:00:54,787
bei s centimeters or two feet
7
00:00:54,788 --> 00:01:00,626
F or data centers with the raised access floor, this is a very common solution
8
00:01:00,927 --> 00:01:05,464
Most data centers use racks
are 4211 in
9
00:01:05,465 --> 00:01:10,769
but some data centers do deploy taller racks being 4811 or beyond
10
00:01:10,770 --> 00:01:14,206
the logic behind this
the higher the rack
11
00:01:14,207 --> 00:01:17,943
the more equipment that
can be placed into these racks
12
00:01:17,944 --> 00:01:22,181
But there are a few important considerations
13
00:01:22,182 --> 00:01:28,287
F irst of all, can you reach the top of the rack safely while installing equipment ^
14
00:01:28,288 --> 00:01:33,926
It is not advisable to have individuals standing on a flimsy box or ladder
15
00:01:33,927 --> 00:01:39,731
trying to install equipment at the top of the rack, since that is a safety risk
16
00:01:39,732 --> 00:01:45,904
Secondly far data centers which
deploy cooling by using the raised floor
17
00:01:45,905 --> 00:01:49,875
you need to ensure that the air which comes out ot the raised floor
18
00:01:50,143 --> 00:01:52,277
can reach the top of the rack
19
00:01:52,278 --> 00:01:58,117
This means that tor higher racks you need more pressure under the raised floor
20
00:01:58,118 --> 00:02:02,621
which in turn means that the cod air that comes out of the raised floor
21
00:02:02,622 --> 00:02:05,557
needs to be at a higher velocity
22
00:02:06,092 --> 00:02:09,795
This could result in the
equipment at the bottom
23
00:02:09,796 --> 00:02:10,295
part of the rack being
24
00:02:10,296 --> 00:02:12,464
part of the rack being partially bypassed
25
00:02:12,465 --> 00:02:16,735
and therefore, leading to potential cooling issues
26
00:02:16,736 --> 00:02:27,346
The unit RU or U is defined as 44 55 mm, or 1 Z5 inch
27
00:02:27,347 --> 00:02:31,884
So again, 19 inch racks have an outside dimension
28
00:02:31,885 --> 00:02:35,854
of approximately 60 cm or 2 ft in width
29
00:02:35,855 --> 00:02:41,960
which allows these racks to be aligned with the raised access floor tiles
30
00:02:41,961 --> 00:02:44,663
which are of similar dimension
31
00:02:44,931 --> 00:02:50,802
In terms of the depth of the rack there's a large variety of depths to choose from
32
00:02:50,803 --> 00:02:53,705
and in order to select the correct one
33
00:02:53,706 --> 00:02:58,210
you have to review the physical
dimension of the ICT equipment
34
00:02:58,211 --> 00:03:00,345
and then choose a rack to match
35
00:03:00,613 --> 00:03:06,985
Obviously, deeper racks will ensure that all types ot equipment will fit in nicely
36
00:03:07,253 --> 00:03:11,523
However, the deeper the rack,
lower the number of racks
37
00:03:11,791 --> 00:03:14,459
that you can place inside the computer room
38
00:03:14,727 --> 00:03:18,163
It is possible to use different rack sizes
39
00:03:18,164 --> 00:03:23,068
within the computer room looking at both the height and the depth of the rack
40
00:03:23,069 --> 00:03:27,272
But commonly data centers tend to use one type of rack
41
00:03:27,273 --> 00:03:30,209
at least in one rack row
42
00:03:30,476 --> 00:03:35,280
So. data centers are deploying twenty tour inch racks
43
00:03:35,548 --> 00:03:40,852
These racks do normally contain the standard nineteen inch equipment
44
00:03:40,853 --> 00:03:46,658
but they are wider to allow tor more cabling to be organised within the rack
45
00:03:46,659 --> 00:03:50,395
Wider racks, similar as deeper racks
46
00:03:50,396 --> 00:03:55,167
will reduce the number of racks that you can place in the computer room
47
00:03:55,435 --> 00:03:58,103
Another potential drawback is.
48
00:03:58,104 --> 00:04:02,341
that when your're using
the traditional raised floor tiles
49
00:04:02,342 --> 00:04:08,213
it will result in a misalignment as can be seen on this particular slide
50
00:04:08,214 --> 00:04:12,718
The rack row on the left hand side is matching the floor tiles
51
00:04:12,719 --> 00:04:18,857
whereas the rack row on the right hand side no longer has the one to one ratio
52
00:04:19,092 --> 00:04:22,527
This may result in a small inconvenience
53
00:04:22,528 --> 00:04:26,531
in the case of the racks
having a different heat load
54
00:04:26,532 --> 00:04:30,502
This normally results
in using different floor tiles,
55
00:04:30,503 --> 00:04:33,438
by looking at the perforation of the tile
56
00:04:33,439 --> 00:04:37,175
in order to match the corresponding heat load in the rack
57
00:04:37,443 --> 00:04:41,980
In other words, if there is more perforation in the tile
58
00:04:41,981 --> 00:04:47,586
it allows for a higher volume of cold air to be pushed in the front of the rack
59
00:04:47,587 --> 00:04:53,425
More information on these tiles will follow in the CDCS course
60
00:05:09,709 --> 00:05:14,212
Rack types are categorized in two post and tour post racks
61
00:05:14,480 --> 00:05:17,683
Two post racks are similar to dual frames
62
00:05:17,684 --> 00:05:21,386
and should only be used for patch panel type of applications
63
00:05:21,387 --> 00:05:27,025
and only in fully secured environments since anything in the rack is exposed
64
00:05:27,293 --> 00:05:31,763
Note also that these racks
heed to be botled to the floor
65
00:05:31,764 --> 00:05:36,001
which may be a challenge in some data centre environments
66
00:05:36,269 --> 00:05:41,073
Four post racks are perfectly
suited for ICT equipment
67
00:05:41,074 --> 00:05:47,479
They come with a variety ot door types at both the front and back of the rack
68
00:05:47,747 --> 00:05:51,450
The type that you wish to use in your data center
69
00:05:51,451 --> 00:05:54,653
depends on the security and cooling requirements
70
00:05:54,654 --> 00:05:58,123
which will be discussed
on the following slides.
71
00:05:58,391 --> 00:06:04,496
One option is the glass door type of rack which can be seen on this slide
72
00:06:04,497 --> 00:06:07,933
from a security point
of view a decent rack
73
00:06:07,934 --> 00:06:14,306
since nobody can touch the equipment or stick a sharp object through the door
74
00:06:14,574 --> 00:06:18,543
The main concern, however with this type ot rack is cooling
75
00:06:18,544 --> 00:06:19,044
When using a traditional
76
00:06:19,045 --> 00:06:22,013
When using a traditional raised floor set up
77
00:06:22,014 --> 00:06:25,484
and having a perforated
tile in front of the rack.
78
00:06:25,485 --> 00:06:31,056
the cold air cannot enter the rack due to the glass door being present
79
00:06:31,324 --> 00:06:34,259
The only way to get cold air into the rack
80
00:06:34,527 --> 00:06:37,696
is by having an opening
undermeath the rack
81
00:06:37,964 --> 00:06:42,234
Doing so you have to make sure
that the opening under the rack.
82
00:06:42,468 --> 00:06:46,705
where the cold air enters
is directed to the front part of the rack
83
00:06:46,706 --> 00:06:52,577
since that is the location where the cold air needs to enter the equipment
84
00:06:52,578 --> 00:06:58,984
The hot air from the ICT equipment is leaving the rack somewhat via back door
85
00:06:59,218 --> 00:07:02,421
which commonly has some ventilation outlets
86
00:07:02,422 --> 00:07:06,925
Most of the heat load
is extacterd via the fan assembly
87
00:07:06,926 --> 00:07:09,060
which is at the top of the rack
88
00:07:09,295 --> 00:07:13,298
The air volume extraction capability of this fan assembly
89
00:07:13,299 --> 00:07:18,336
will ultimately determine the maximum heat load that you can place in the rack
90
00:07:18,337 --> 00:07:23,108
which is often limited to a few kilowatts per rack only
91
00:07:23,376 --> 00:07:26,845
Also, the older type of glass door racks
92
00:07:26,846 --> 00:07:32,684
may not have a fan assembly built in but it can be retrofitted
93
00:07:32,985 --> 00:07:37,722
Another minor concern the door being mainly glass
94
00:07:37,723 --> 00:07:41,726
it is more prone to accidental damage
95
00:07:41,961 --> 00:07:50,502
Perforated or grated dual racks have surface opening of typically ?0 45%
96
00:07:50,503 --> 00:07:55,540
this will allow for a good amount of air flow to go through the door of the racks
97
00:07:55,541 --> 00:08:01,680
and therefore, entering the ICT equipment
allowing for good cooling capacity
98
00:08:01,981 --> 00:08:04,883
These types of racks can hold up to
99
00:08:04,884 --> 00:08:09,154
five kilowatt of heat load
100
00:08:09,388 --> 00:08:13,625
Obviously the door needs to be unobstructed
101
00:08:13,626 --> 00:08:14,860
and therefore, no stickers
102
00:08:14,861 --> 00:08:17,896
and therefore, no stickers or papers should be present
103
00:08:18,164 --> 00:08:23,735
It is not unusual to see computer rooms where there are papers in a folder
104
00:08:23,769 --> 00:08:26,671
hanging on a paper clip on the inside of the door
105
00:08:26,672 --> 00:08:30,375
and this will obviously
hinder the air flow
106
00:08:30,376 --> 00:08:33,812
Some perforated doors have quite big openings
107
00:08:33,813 --> 00:08:38,884
which some organizations consider to be posing a higher level of risk
108
00:08:39,151 --> 00:08:43,955
whereby someone could potentially stick a sharp object through the door
109
00:08:44,190 --> 00:08:47,392
Whether this is really a risk depends on
110
00:08:47,393 --> 00:08:50,295
the overall security
management of the room
111
00:08:50,296 --> 00:08:52,964
in which the racks are being placed
112
00:08:52,965 --> 00:08:57,235
In an enterprise data center
the risk is relatively low.
113
00:08:57,236 --> 00:09:02,807
since only a handful of authorized staff members are allowed in the computer room
114
00:09:03,075 --> 00:09:07,646
However, in a commercial data center in a shared computer room
115
00:09:07,647 --> 00:09:11,616
the risk could be higher having potentially a lot of movement
116
00:09:11,884 --> 00:09:15,620
depending on the number of customers, contractors
117
00:09:15,855 --> 00:09:20,125
staff that are having access
to that particular room
118
00:09:20,426 --> 00:09:27,032
Mesh door racks have a large surface opening of up to eighty five percent
119
00:09:27,033 --> 00:09:31,836
This will allow for a large amount of air flow to pass through the rack
120
00:09:31,837 --> 00:09:35,540
and therefore providing an excellent cooling capacity
121
00:09:35,808 --> 00:09:41,913
Configurations of up to fifteen kilowatts can be deployed in this type of rack
122
00:09:41,914 --> 00:09:45,116
Although it has a large surface opening
123
00:09:45,117 --> 00:09:50,989
due to the mesh structure
it still provides good levels of security
124
00:09:51,324 --> 00:09:54,726
This is the type of rack that is considered
125
00:09:54,727 --> 00:09:57,128
modern computer rooms
126
00:09:57,129 --> 00:09:58,463
modern comouter rooms
127
00:09:58,731 --> 00:10:05,103
Some type of racks come with|
casters of feet at the base of the rack
128
00:10:05,104 --> 00:10:09,874
This creates a point load on the floor and as previously discussed
129
00:10:10,176 --> 00:10:13,078
it is: therefore, not always desirable
130
00:10:13,346 --> 00:10:18,149
hich have their frame as the base of the rack, are bet
131
00:10:18,150 --> 00:10:20,518
since they fit nicely on the floor.
132
00:10:20,519 --> 00:10:24,522
and create a reasonable distribution
of the weight load of the rack,
133
00:10:24,523 --> 00:10:30,128
Especially when the width of the rack
is matching the floor tile dimension
134
00:10:30,129 --> 00:10:32,263
If you are using casters or feet
135
00:10:32,264 --> 00:10:36,234
be aware that there will be a gap
between the rack and the floor.
136
00:10:36,235 --> 00:10:41,072
which potentially creates leakage in terms ot cold and hot air
137
00:10:41,073 --> 00:10:44,009
from the front and the back of the rack
138
00:10:44,276 --> 00:10:50,382
To prevent the mixing of cold and hot an which will result in inefficiencies
139
00:10:50,383 --> 00:10:55,720
you should consider closing this gap by using skirting at the base of the rack
140
00:10:55,721 --> 00:10:59,724
and therefore, closing the gap
between the floor and the rack
141
00:10:59,725 --> 00:11:05,530
This is definitely a requirement when you are deploying containment solutions
142
00:11:05,798 --> 00:11:10,869
Containment will be discussed in the cooling infrastructure module
143
00:11:11,404 --> 00:11:15,106
Racks are commonly
black or white in color
144
00:11:15,107 --> 00:11:19,911
with some variants like grey or vanilla style color
145
00:11:20,179 --> 00:11:24,182
Most data centers like to use the black color racks
146
00:11:24,183 --> 00:11:27,085
since it looks nice in a computer room
147
00:11:27,353 --> 00:11:33,191
Realize however, that while doing so it does impact the overall light strength
148
00:11:33,192 --> 00:11:36,094
especially in the lower part of the rack
149
00:11:36,362 --> 00:11:39,030
So looking from a light perspective
150
00:11:39,031 --> 00:11:43,001
it is, therefore, better
to use white color racks
151
00:11:43,002 --> 00:11:46,237
this since white is reflective
152
00:11:46,238 --> 00:11:50,208
In addition, it may introduc savings on the lights
153
00:11:50,209 --> 00:11:52,877
being used in your computer room
154
00:12:15,868 --> 00:12:18,236
All racks are ideally locked
155
00:12:18,237 --> 00:12:22,006
both the front and the back
to provide adequate security
156
00:12:22,274 --> 00:12:27,011
Some data center managers may argue that the computer is already secure?
157
00:12:27,279 --> 00:12:31,282
and therefore racks no longer have a need to be individually secured
158
00:12:31,817 --> 00:12:33,952
Although this may sound logical
159
00:12:33,953 --> 00:12:38,189
the question is whether anybody who comes through the computer room door
160
00:12:38,190 --> 00:12:42,994
is allows to touch any equipment in any rack within the computer room
161
00:12:43,529 --> 00:12:48,099
If such is not the case all racks must be blocked
162
00:12:48,367 --> 00:12:53,171
Realize that in an operational
data center on regular occasion
163
00:12:53,405 --> 00:12:56,641
external staff is working in the computer room
164
00:12:56,642 --> 00:12:58,443
and this could pose a risk
165
00:12:58,978 --> 00:13:04,048
By default, a rack that comes with the lock is based on a key
166
00:13:04,049 --> 00:13:06,718
whereby one key fits all
167
00:13:06,952 --> 00:13:09,087
If requirements exist
168
00:13:09,088 --> 00:13:12,023
you may have a need for
, to avoid that
169
00:13:12,024 --> 00:13:14,392
one single key opens all racks
170
00:13:14,393 --> 00:13:18,396
but do realize that with many keys available
171
00:13:18,397 --> 00:13:21,332
key management may become a nightmare
172
00:13:21,600 --> 00:13:25,870
As an alternative you could consider using electronic locks
173
00:13:25,871 --> 00:13:28,773
such as locks with the security pin coder
174
00:13:29,008 --> 00:13:33,545
biometrics, which is a unique part of the body for authentication
175
00:13:34,113 --> 00:13:37,582
and access card or other electronic means
176
00:13:38,083 --> 00:13:40,718
This will be easier to manage and monitor
177
00:13:40,719 --> 00:13:45,757
since every entry into a rack
can be recorded in the log file,
178
00:13:45,758 --> 00:13:48,159
which will allow you to track and trace
179
00:13:48,160 --> 00:13:52,397
who had access to the rack and when the access occurred
180
00:13:53,232 --> 00:13:58,036
As you can imagine electronic locks provide great functionality
181
00:13:58,037 --> 00:14:02,006
but ther are more costly
han the traditional key locks
182
00:14:02,808 --> 00:14:06,845
Flower rails or power strips as they are often referred to
183
00:14:06,846 --> 00:14:13,184
come in a wide variety of types each with their own functionality and price tag
184
00:14:13,719 --> 00:14:16,921
It is important to understand
the business requirements
185
00:14:16,922 --> 00:14:21,693
before deciding on the strategy for purchasing power rails
186
00:14:22,228 --> 00:14:30,201
Remember that each rack has at least one but more often two or four power rails
187
00:14:30,502 --> 00:14:36,941
hence, every dollar extra per power rail can quickly add up to a large amount
188
00:14:37,743 --> 00:14:43,047
One type of power rail is the one with the traditional standard power outlets
189
00:14:43,849 --> 00:14:46,751
these rails provide only connectivity
190
00:14:46,752 --> 00:14:51,789
but provides no protection, measurements or other functionality
191
00:14:52,091 --> 00:14:55,793
this type of power level is the
192
00:14:56,595 --> 00:14:58,229
Another power rail option
193
00:14:58,497 --> 00:15:05,136
is the one whereby each outlet has an indicator to whether the power is on/off
194
00:15:05,938 --> 00:15:09,440
These power rails are commonly equipped with the fuse
195
00:15:09,441 --> 00:15:12,343
to protect each individual outlet,
196
00:15:12,845 --> 00:15:14,746
this could potentially ensure
197
00:15:14,747 --> 00:15:18,449
that it the device creates a short circuit or overload
198
00:15:18,450 --> 00:15:21,119
then it does not affect the entire power rail
199
00:15:21,353 --> 00:15:27,258
Be aware that some types ot power plug already have a fuse protection built in
200
00:15:27,493 --> 00:15:33,064
if so, the fuse protection in the
power rail may not be required.
201
00:15:33,599 --> 00:15:38,369
Another type of power rail is the one
which has a built-in power meter.
202
00:15:38,904 --> 00:15:44,742
these meters can indicate the various power parameters, such as voltage
203
00:15:44,743 --> 00:15:49,247
ampere, the power factor
and other useful parameters.
204
00:15:49,515 --> 00:15:54,852
The high end type of power rails very likely has a network connection built in
205
00:15:54,853 --> 00:15:59,090
which allows you to monitor and or control the power rail
206
00:15:59,625 --> 00:16:01,259
Depending on the type of model
207
00:16:01,260 --> 00:16:05,763
it may be able to monitor at the individual outlet level
208
00:16:06,298 --> 00:16:11,869
this provides great functionality such as having a remote power cycling capabilities
209
00:16:11,870 --> 00:16:14,272
and other useful features
210
00:16:14,773 --> 00:16:18,509
Realize though that these power rails are much higher in cost
211
00:16:18,777 --> 00:16:21,412
so given the total number of racks
212
00:16:21,413 --> 00:16:25,149
and the fact that most racks require multiple power rails
213
00:16:25,150 --> 00:16:30,221
it is easy to understand that the
investment cost is quite substantial.
214
00:16:31,023 --> 00:16:36,327
Power rails are available in various configurations, such as single phase
215
00:16:36,328 --> 00:16:40,832
three phase and three phase input which is then split over
216
00:16:40,833 --> 00:16:44,836
three individual parts of the railway single phase outlets
217
00:16:44,837 --> 00:16:50,408
as well as some three phase output at any combination that you can think ot
218
00:16:51,210 --> 00:16:54,679
These kind of power hills offer great flexibility
219
00:16:54,680 --> 00:16:58,082
create a better balance
220
00:16:58,083 --> 00:17:01,285
within the three phases inside the rack
221
00:17:01,820 --> 00:17:06,357
F inally, there are some additional
222
00:17:06,859 --> 00:17:10,862
Many racks have fan assemblies at the top of the rack
223
00:17:11,397 --> 00:17:17,502
using these fans, however, should only be done when using glass door based racks
224
00:17:18,070 --> 00:17:22,373
When you are using the ventilated doors, such as mesh doors
225
00:17:22,374 --> 00:17:25,009
then you will need to turn those fans off
226
00:17:25,010 --> 00:17:28,479
since they will disturb the tront to the rear air movement
227
00:17:29,014 --> 00:17:33,251
For racks which are installed
in seismic prone areas,
228
00:17:33,252 --> 00:17:36,187
adequate measures need to be taken
229
00:17:36,722 --> 00:17:38,556
If you are using bracing
230
00:17:38,557 --> 00:17:40,958
physical securing of all items
231
00:17:40,959 --> 00:17:44,729
you need to identify the type
of connection or fixing options
232
00:17:44,730 --> 00:17:46,831
that are available on the rack
233
00:17:47,599 --> 00:17:50,535
In that case you also need to make sure
234
00:17:50,536 --> 00:17:53,738
that the racks are meeting the seismic requirements
235
00:17:53,739 --> 00:17:58,476
to handle the physical force
which they may get exposed to.
236
00:17:59,011 --> 00:18:02,747
Ranking panels will help in creating a good separation
237
00:18:03,482 --> 00:18:04,882
between hot and cool aisles
238
00:18:04,883 --> 00:18:09,387
and this will have a positive effect on energy efficiencies
239
00:18:09,888 --> 00:18:13,925
flanking panels should be installed in every rack space
240
00:18:13,926 --> 00:18:17,128
where there is no equipment installed
241
00:18:17,663 --> 00:18:24,035
The metal panels tend to be more expensive? and could still conduct hot and cold air
242
00:18:24,036 --> 00:18:26,704
since metal is a good heat conductor
243
00:18:27,239 --> 00:18:32,310
expensive and provide good insulation
244
00:18:32,311 --> 00:18:37,615
but you need to make sure that this
type meets the local tire regulations
245
00:18:38,417 --> 00:18:42,153
Make sure that your rack
rows areas long as possible,
246
00:18:42,154 --> 00:18:45,289
so to make the row act like a wall
247
00:18:45,290 --> 00:18:49,627
this to prevent the mixing of cold and hot air to take place
248
00:18:50,362 --> 00:18:56,200
And while doing so, you have to consider the local fire safety regulation
249
00:18:56,201 --> 00:19:00,004
to make sure that escape paths are still in adequate
250
00:19:00,539 --> 00:19:02,640
In this module, you have learned
251
00:19:02,641 --> 00:19:06,911
that there are many choices
available for equipment racks
252
00:19:06,912 --> 00:19:07,945
rack you should consider
253
00:19:07,946 --> 00:19:09,814
and that the type ot rack you should consider
254
00:19:09,815 --> 00:19:12,216
depends on the ICT equipment
255
00:19:12,217 --> 00:19:14,585
as well as the room layout
256
00:19:15,654 --> 00:19:22,059
Different type of racks and doors have
an impact on security, as well as cooling
257
00:19:22,628 --> 00:19:27,365
Various types of security and
power rail options are available,
258
00:19:27,366 --> 00:19:30,835
each with their own options and characteristics
259
00:19:31,370 --> 00:19:34,038
Investigate the business requirements
260
00:19:34,039 --> 00:19:38,543
since often a computer is equipped with many racks and power rails
261
00:19:38,544 --> 00:19:41,479
so every dollar more per rack
262
00:19:41,480 --> 00:19:46,784
or power rail will result in a much larger investment requirement
263
00:22:12,197 --> 00:22:26,977
Energy Storage
264
00:22:36,421 --> 00:22:40,124
This slide demonstrates data from research
265
00:22:40,158 --> 00:22:43,861
which presents the influence of environmental factors
266
00:22:43,862 --> 00:22:48,399
and the impact it has on electrons components on a printed circuit board
267
00:22:48,667 --> 00:22:50,267
As can be concluded
268
00:22:50,268 --> 00:22:55,606
temperature and humidity are the factors creating a major part of the problems
269
00:22:55,841 --> 00:22:58,242
for reliability of electronics
270
00:22:58,510 --> 00:23:03,848
Cooling is the number one issue in today's data centers, and in some cases
271
00:23:03,849 --> 00:23:09,153
there is little understanding present on how to properly control the data center
272
00:23:09,688 --> 00:23:15,259
Lack of proper cooling in the computer room is the result of a number of reasons
273
00:23:15,260 --> 00:23:17,628
such as changes in the setup
274
00:23:17,629 --> 00:23:21,098
issues created along the
life cycle of the data center
275
00:23:21,366 --> 00:23:25,369
misunderstanding of cooling principles, etc etc
276
00:23:25,904 --> 00:23:26,937
Traditionally
277
00:23:26,938 --> 00:23:32,810
cooling takes up as much as 30% of the total power consumption of a data center
278
00:23:33,078 --> 00:23:36,547
It is therefore not surprising that more data centers
279
00:23:36,548 --> 00:23:41,585
are looking into how they can create a more efficient cooling infrastructure
280
00:23:41,586 --> 00:23:45,022
in order to drive the power consumption down
281
00:23:45,023 --> 00:23:50,594
which will result in cost savings as well as being more environmentally friendly
282
00:23:50,896 --> 00:23:54,565
When cooling ICT equipment in a data center
283
00:23:54,566 --> 00:23:57,768
two important factors must be considered
284
00:23:57,769 --> 00:24:01,472
which are temperature
and air volume displacement
285
00:24:02,007 --> 00:24:06,510
looking at the temperature the American Society of Heating
286
00:24:06,845 --> 00:24:11,849
Refrigerating and Air Conditioning Engineers shortly known as ASHRAI
287
00:24:11,850 --> 00:24:16,387
the Technical committee
9 9 is guiding the industry
288
00:24:16,388 --> 00:24:22,226
on the recommended and allowable
temperature and humidity for ICT equipment
289
00:24:22,494 --> 00:24:29,133
In 2011, ASHRAE indicated the recommended values for ICT equipment in the computer rcxxn
290
00:24:29,401 --> 00:24:33,637
to be in the range of 18- 27 degrees Celsius
291
00:24:33,638 --> 00:24:38,976
which is equivalent to 65-81 degrees Fahrenheit
292
00:24:39,244 --> 00:24:44,582
The values are anticipated to be extended in the upcoming years
293
00:24:44,583 --> 00:24:49,887
which will allow for more parts of the world to make use of free coolinq
294
00:24:50,388 --> 00:24:55,459
It is a common mistake in data centers for operations staff to assume'
295
00:24:55,460 --> 00:24:59,163
that the temperature, which
is set on the air conditioner,
296
00:24:59,164 --> 00:25:03,167
is the temperature which will be supplied to the ICT systems
297
00:25:04,803 --> 00:25:05,302
This is incorrect
298
00:25:05,303 --> 00:25:08,205
The temperature set point ot an air conditioner
299
00:25:08,206 --> 00:25:11,175
is based on the return air temperature?
300
00:25:11,443 --> 00:25:17,014
In simplified terms, the air conditioner measures the air intake temperature'
301
00:25:17,015 --> 00:25:19,950
and matches it with the setpoint
302
00:25:20,218 --> 00:25:25,856
This means that if you set the
temperature to 22 degrees Celsius
303
00:25:25,857 --> 00:25:28,726
equivalent to 72 degrees Fahrenheit
304
00:25:28,727 --> 00:25:32,730
the air conditioner tries to
cool the area in such a way
305
00:25:32,731 --> 00:25:36,934
that the return temperature is 22 degrees Celsius
306
00:25:37,469 --> 00:25:42,573
Therefore, this result in a much lower temperature leaving the air conditioner
307
00:25:42,574 --> 00:25:47,044
which is the temperature of the
air flow supplied to the ICT systems
308
00:25:47,612 --> 00:25:53,751
Because of this; it is important to measure the intake temperature on the ICT equipment
309
00:25:54,019 --> 00:25:57,988
which should be within the
ASHRAE recommended range
310
00:25:57,989 --> 00:26:02,493
and compare that with the return temperature at the air conditioner level
311
00:26:03,061 --> 00:26:08,332
This may result, for example in the set point being 27 degrees Celsius
312
00:26:08,333 --> 00:26:10,234
as the return temperature
313
00:26:10,502 --> 00:26:16,073
whereas at the same time the ICT equipment is having an intake temperature
314
00:26:16,074 --> 00:26:18,709
of 23 degrees Celsius
315
00:26:19,511 --> 00:26:24,348
looking at humidity ASHRAE has made changes between the values
316
00:26:24,616 --> 00:26:27,751
for the 2008 and 2012 standards
317
00:26:28,019 --> 00:26:31,221
The current values are indicated in this slide
318
00:26:31,489 --> 00:26:37,895
The low end moisture has been lowered to 9 degrees Celsius dew point
319
00:26:38,163 --> 00:26:42,099
Be aware that a relative
humidity below 40%
320
00:26:42,367 --> 00:26:46,637
will increase potential issues with electrostatic discharge
321
00:26:46,638 --> 00:26:49,306
shortly known as ESD
322
00:27:20,705 --> 00:27:21,438
IT and network electronic equipment
323
00:27:21,439 --> 00:27:22,573
IT and network electronic, equipment
324
00:27:22,574 --> 00:27:23,874
IT and network electronic equipment
325
00:27:23,875 --> 00:27:27,344
will suffer reliability
problems as it heats up
326
00:27:27,612 --> 00:27:32,683
And because of that, it is important to keep equipment at its proper temperature
327
00:27:32,951 --> 00:27:38,789
This graph explains the expected lite span of a central processing unit or CPU
328
00:27:39,057 --> 00:27:43,560
at different temperature levels indicated in temperature Celsius
329
00:27:44,095 --> 00:27:46,997
The graph explains that the microprocessor
330
00:27:46,998 --> 00:27:50,734
can operate in 95 degrees (Celsius environmental temperature
331
00:27:50,969 --> 00:27:54,171
which is equivalent to
200 degrees Fahrenheit,
332
00:27:54,439 --> 00:27:58,208
but if it would, it could not last more than a couple of years
333
00:27:58,443 --> 00:28:01,111
A high temperature is fatal
334
00:28:01,112 --> 00:28:05,082
since it will reduce the life span of the equipment
335
00:28:05,350 --> 00:28:09,620
I here is some confusion about the temperature in the data center
336
00:28:09,888 --> 00:28:13,357
Some believe that the ambient
temperature in the data center
337
00:28:13,358 --> 00:28:18,395
should be around 20 degrees
Celsius or 68 degrees Fahrenheit
338
00:28:18,396 --> 00:28:20,264
but this is not correct
339
00:28:20,532 --> 00:28:25,302
Cold air needs to be delivered
at the intake of the equipment.
340
00:28:25,303 --> 00:28:26,904
and following ASHRAf
341
00:28:26,905 --> 00:28:32,209
this means delivering a temperature that is between 18 and 27 degrees Celsius
342
00:28:32,210 --> 00:28:36,213
or 65 to 81 degrees F ahrenheit
343
00:28:36,481 --> 00:28:41,785
Hardware manufacturers are moving beyond fans and adopt cooling mechanisms
344
00:28:41,786 --> 00:28:42,519
liquid cooling systems
345
00:28:42,520 --> 00:28:45,222
such as radiators and liquid cooling systems
346
00:28:45,223 --> 00:28:47,925
to avoid potential overheating
347
00:28:48,193 --> 00:28:53,230
As a result of downsizing the
physical size of computer equipment
348
00:28:53,231 --> 00:28:59,603
today’s systems are getting so hot that it is almost impossible to cool it with air
349
00:29:00,171 --> 00:29:05,209
With the microprocessor getting hotter and a significant smaller computer chassis
350
00:29:05,477 --> 00:29:12,649
there is less ability or less volume of air being able to push through the system
351
00:29:13,184 --> 00:29:18,789
Cooling capacity is expressed in many units, such as British Thermal Unit
352
00:29:18,790 --> 00:29:20,624
shortly known as BTU
353
00:29:20,625 --> 00:29:23,260
horsepower, ton, etcetera
354
00:29:23,528 --> 00:29:29,700
In practice, it wouldd be easier if everyone' uses the same unit to measure heat
355
00:29:29,701 --> 00:29:31,535
which is kilowatts
356
00:29:31,803 --> 00:29:36,340
obvious, since power and ICT load
357
00:29:36,341 --> 00:29:38,976
are dimensioned in the same unit of measure
358
00:29:38,977 --> 00:29:42,980
and therefore it makes it easier to perform calculations
359
00:29:42,981 --> 00:29:45,082
on the need for your cooling
360
00:29:45,350 --> 00:29:50,988
There are two types ot heat loads known as sensible heat and latent heat
361
00:29:51,222 --> 00:29:54,124
Sensible heat is the type ot heat load
362
00:29:54,125 --> 00:29:57,294
that causes a temperature
363
00:29:57,862 --> 00:29:59,963
In the context of a data center
364
00:29:59,964 --> 00:30:04,501
an ICT system heats up due to power entering the system
365
00:30:05,003 --> 00:30:09,306
During this process, there is no moisture involved
366
00:30:09,808 --> 00:30:12,476
Therefore, sensible capacity
367
00:30:12,477 --> 00:30:17,781
is described as the capacity to lower the temperature in an object
368
00:30:17,782 --> 00:30:21,752
The other type of heat load is called latent heat
369
00:30:22,320 --> 00:30:27,124
I atent heat load causes a substance to change a state
370
00:30:27,358 --> 00:30:32,663
An example is boiling water, which when water reaches boiling point
371
00:30:32,664 --> 00:30:35,632
the water will evaporate into steam
372
00:30:35,867 --> 00:30:39,069
Humans are also creating latent heat
373
00:30:39,070 --> 00:30:41,438
as they produce heat and moisture
374
00:30:41,706 --> 00:30:45,709
Think of working out in the
gym or jogging in the park
375
00:30:45,710 --> 00:30:49,713
which causes the body to heat up and throwing out moisture
376
00:30:49,714 --> 00:30:52,616
which is the body transpiration
377
00:31:10,301 --> 00:31:15,072
Comfort air conditioners have a low sensible heat load capability
378
00:31:15,373 --> 00:31:20,110
These types of air conditioners are commonly used in areas where humans are present
379
00:31:20,111 --> 00:31:22,813
and humans generate latent heat
380
00:31:22,814 --> 00:31:26,216
A comfort air conditioner has no humidity control
381
00:31:26,217 --> 00:31:31,288
and therefore lacks the capability to manage the humidity in an area
382
00:31:31,556 --> 00:31:35,792
With the objective of cooling areas occupied by humans
383
00:31:35,793 --> 00:31:40,330
comfort air conditioners are not designed for continuous operations
384
00:31:40,598 --> 00:31:43,267
running twenty tour hours per day
385
00:31:43,268 --> 00:31:47,771
The filter sections in this type of air conditioner are commonly more aimed at
386
00:31:47,772 --> 00:31:50,941
protecting the internals of the air conditioner itself
387
00:31:50,942 --> 00:31:54,411
rather than protecting its target area trom dust
388
00:31:54,412 --> 00:31:59,950
and hence they lack the proper filter capabilities for computer rooms
389
00:32:00,251 --> 00:32:06,156
Furthermore, these units normally lac k the control and monitoring interfaces
390
00:32:06,157 --> 00:32:09,092
unless additional sensors are installed
391
00:32:09,394 --> 00:32:14,131
Also,these units normally
don’t have a control input
392
00:32:14,432 --> 00:32:18,936
which allows the unit
to be shut it down remotely.
393
00:32:18,937 --> 00:32:24,508
This is a potential issue in situations such as a fire in an area
394
00:32:24,509 --> 00:32:28,245
where the air conditioner equipment needs to shut down
395
00:32:28,246 --> 00:32:32,783
before a discharge of fire suppression gas takes place
396
00:32:33,318 --> 00:32:38,889
Precision air conditioners are designed for areas such as a computer room
397
00:32:38,890 --> 00:32:42,592
They have a high sensible
heat load capability,
398
00:32:42,593 --> 00:32:48,732
which matches very well the type of heat that is generated in the computer room
399
00:32:49,000 --> 00:32:52,169
Precision air conditioners
are equipped with
400
00:32:52,170 --> 00:32:56,173
a controlled temperature and humidification capability
401
00:32:56,174 --> 00:32:59,643
and are therefore able to provide prec ise
402
00:32:59,644 --> 00:33:03,347
and stable cooling and humidity capabilities
403
00:33:03,614 --> 00:33:07,084
These units are equipped
with proper filters,
404
00:33:07,085 --> 00:33:11,321
which not only protect the air conditioner equipment itself
405
00:33:11,322 --> 00:33:17,694
but it also often provides adequate filtering for the computer room as well
406
00:33:17,962 --> 00:33:24,568
Also these units are designed and manufactured for continuous operation
407
00:33:24,569 --> 00:33:27,571
which meets the requirements of the computer room
408
00:33:27,572 --> 00:33:33,410
where your ICT equipment is also operating 24/7
409
00:33:33,611 --> 00:33:38,181
Furthermore, precision air conditioners are commonly equipped
410
00:33:38,182 --> 00:33:41,885
with very good monitoring interface capabilities
411
00:33:41,886 --> 00:33:44,254
allowing high level interfacing
412
00:33:44,255 --> 00:33:48,792
so that various parameters can be remotely monitored
413
00:33:48,793 --> 00:33:54,398
For fire scenarios, they also have an emergency "power off interface contact
414
00:33:54,399 --> 00:33:57,534
which allows you to connect
the air conditioner unit,
415
00:33:57,535 --> 00:33:59,970
to the fire detection panel
416
00:33:59,971 --> 00:34:03,974
and therefore shutdown
the air conditioner automatically
417
00:34:03,975 --> 00:34:08,178
before the discharge of fire suppression gas takes place
418
00:34:08,980 --> 00:34:14,284
This slide explains the four main components of an air conditioner
419
00:34:14,552 --> 00:34:20,724
The evaporator consists of a grill through which some form of cold liquids
420
00:34:20,725 --> 00:34:23,860
usually a refrigerant is flowing
421
00:34:23,861 --> 00:34:26,797
On one side of the grill
422
00:34:26,798 --> 00:34:30,801
warm air is coming in and it is passed through the grill
423
00:34:31,069 --> 00:34:33,970
after which the heat will be extracted
424
00:34:33,971 --> 00:34:38,542
As a result it will be cool
on the backside of the grill.
425
00:34:38,776 --> 00:34:44,915
The laws of energy dictate that the energy can’t just appear or disappear
426
00:34:44,916 --> 00:34:50,754
It is always transforming so the heat that is rejected through the evaporator
427
00:34:50,755 --> 00:34:53,690
has to go into another medium
428
00:34:53,958 --> 00:34:57,394
That process is handled by the condenser
429
00:34:57,395 --> 00:35:02,732
This is the unit that transforms the extracted heat into another medium
430
00:35:02,733 --> 00:35:06,203
which is commonly in the open air
431
00:35:06,471 --> 00:35:09,372
The compressor keeps the refrigerant flowing through
432
00:35:09,674 --> 00:35:12,576
the system at specific flow rates and pressure
433
00:35:12,577 --> 00:35:17,047
whereas the expansion valve controls the quantity of the refrigerant
434
00:35:17,048 --> 00:35:20,250
that is flowing into the evaporator
435
00:35:20,251 --> 00:35:25,622
A refrigerant is a chemical compound that is used as the heat carrier
436
00:35:25,623 --> 00:35:32,262
which changes from gas to liquid and then back to gas in the refrigeration cycle
437
00:35:32,463 --> 00:35:36,533
Refrigerants are used primarily in refrigerators
438
00:35:36,534 --> 00:35:40,237
freezers, air conditioning
but also heat pumps.
439
00:35:40,471 --> 00:35:44,474
Refrigerants play a key role in cold production
440
00:35:44,742 --> 00:35:49,513
Refrigerant with a phase change from liquid to vapour
441
00:35:49,514 --> 00:35:53,783
receives the heat required trom a substance at a low temperature
442
00:35:53,784 --> 00:35:57,220
to change its phase, and so produce cold
443
00:35:57,221 --> 00:36:00,690
With the phase change from vapour to liquid
444
00:36:00,992 --> 00:36:05,195
the refrigerant also transfers
its phase changed heat
445
00:36:05,196 --> 00:36:08,431
to another substance at a higher temperature
446
00:36:08,933 --> 00:36:13,737
Regulations may restrict the use of some types of refrigerants
447
00:36:13,738 --> 00:36:19,843
due to their toxicity, flammability their contribution to ozone layer depletion
448
00:36:20,111 --> 00:36:23,313
and their impact on climate change
449
00:36:23,581 --> 00:36:25,949
Freon is a brand name
450
00:36:25,950 --> 00:36:31,488
but it is also a generic descriptor of a fluorocarbon refrigerant
451
00:36:31,489 --> 00:36:36,293
R22 is banned in the United States and the European Union
452
00:36:36,294 --> 00:36:39,496
but still in use in developing countries
453
00:36:39,497 --> 00:36:44,267
It will be phased out by 2040 due to its Global Warming Potential (GWP)
454
00:36:44,268 --> 00:36:47,170
and low ozone depletion characteristics
455
00:36:47,438 --> 00:36:51,942
R410a is considered
the alternative for R22
456
00:36:51,943 --> 00:36:57,314
It is well used in data centers and it is considered more environmentally friendly
457
00:36:57,515 --> 00:37:00,450
It does not contribute
to ozone depletion
458
00:37:00,451 --> 00:37:03,687
but it does have a
Global Warming Potential.
459
00:37:03,955 --> 00:37:08,992
Under the assumption that preventing ozone depletion is more important
460
00:37:08,993 --> 00:37:12,929
in the short term than global warming potential for the short term
461
00:37:12,930 --> 00:37:17,167
R410a is preferable to R22
462
00:37:17,468 --> 00:37:22,806
Refrigerants are greenhouse gases and influence global warming
463
00:37:22,807 --> 00:37:28,912
How much a greenhouse gas influences global warming depends on 3 key factors
464
00:37:29,180 --> 00:37:32,916
The first is. how much of it exists in the atmosphere?
465
00:37:32,917 --> 00:37:37,654
The second is its lifetime how long does it remain in the atmosphere?
466
00:37:37,655 --> 00:37:42,192
The third is. how effective
it is at trapping heat?
467
00:37:42,460 --> 00:37:45,662
This is referred to as its global warming potential
468
00:37:45,663 --> 00:37:48,064
which is a measure of the total energy
469
00:37:48,065 --> 00:37:51,768
that a gas absorbs over a given period ot time
470
00:37:51,769 --> 00:37:57,107
usually hundred years relative to the
emissions of one ton of carbon dioxide
471
00:37:57,375 --> 00:38:02,946
Arguably, therefore, the less (Global
Warming Potential a refrigerant has
472
00:38:02,947 --> 00:38:07,517
the better it is for the environment
and long-term sustainability.
473
00:38:38,149 --> 00:38:42,419
Air cooled and self contained units are normally ceiling cassettes
474
00:38:42,420 --> 00:38:46,423
which hang on the suspended ceiling or are wall mounted
475
00:38:46,624 --> 00:38:49,059
There are two types available
476
00:38:49,060 --> 00:38:53,263
One type still needs a condenser unit outside ot the building
477
00:38:53,264 --> 00:38:57,534
the other as the condenser
unit built into the system,
478
00:38:57,535 --> 00:39:02,038
and it just evaporates the hot air on top ot the suspended ceiling
479
00:39:02,039 --> 00:39:04,974
Although relatively cheap to purchase
480
00:39:04,975 --> 00:39:09,212
this type of air conditioner comes with a high operating costs
481
00:39:09,480 --> 00:39:12,649
For the various reasons mentioned
482
00:39:12,917 --> 00:39:16,386
this type of air conditioner is not recommended
483
00:39:16,387 --> 00:39:20,390
for cooling ICT equipment in a data center
484
00:39:20,658 --> 00:39:26,763
of air conditioner
is known as a split system or DX system
485
00:39:26,764 --> 00:39:29,733
which is short for Direct Expansion
486
00:39:29,734 --> 00:39:35,772
This unit is commonly referred to as a computer room air conditioner or CRAC
487
00:39:35,773 --> 00:39:38,975
or Heating and Ventilation Air Conditioner
488
00:39:38,976 --> 00:39:43,246
shortly known as HVAC
and it is based on refrigerant
489
00:39:43,514 --> 00:39:46,182
The evaporator is in the data center
490
00:39:46,450 --> 00:39:51,755
and from there pipes run to the condenser unit outside the building
491
00:39:52,022 --> 00:39:54,124
Where the building code applies
492
00:39:54,125 --> 00:39:58,895
you should verify if it is allowed to install this type of unit
493
00:39:58,896 --> 00:40:02,132
because certain building
codes do not alow
494
00:40:02,133 --> 00:40:05,602
to place condenser units outside the building
495
00:40:05,836 --> 00:40:10,373
Another potential issue
run.
496
00:40:10,608 --> 00:40:14,077
The distance between the CRAG inside the data center
497
00:40:14,078 --> 00:40:16,479
to the condenser outside ot the building
498
00:40:16,480 --> 00:40:23,620
should not exceed more than 30 35 meters or 90 teet measured horizontally
499
00:40:23,921 --> 00:40:27,090
Exceedig the length of the pipe run will result in
500
00:40:27,091 --> 00:40:30,560
the air conditioner losing out ot cooling capacity
501
00:40:30,795 --> 00:40:35,098
Some vendors are able
to have a longer pipe run,
502
00:40:35,099 --> 00:40:38,802
but you would need to review the technical specifications
503
00:40:38,803 --> 00:40:44,641
to ensure that the pipe run length
is matching the technology deployed
504
00:40:44,942 --> 00:40:47,844
Scalability is relatively easy
505
00:40:47,845 --> 00:40:51,581
so as long as you have floor space available
506
00:40:51,849 --> 00:40:57,420
These units can be easily expanded by adding an additional unit in the room
507
00:40:57,421 --> 00:41:01,658
and an additional condenser outside ot the building
508
00:41:01,659 --> 00:41:04,327
Obviously adding additional units
509
00:41:04,328 --> 00:41:08,298
in a production data center comes with certain risks
510
00:41:08,299 --> 00:41:13,336
which needs to be addressed as part
of the change management procedure
511
00:41:13,604 --> 00:41:16,506
This type of air conditioner is different
512
00:41:16,507 --> 00:41:21,845
instead of being freon based it is using glycol instead
513
00:41:21,846 --> 00:41:26,082
One property of glycol is that it does not freeze
514
00:41:26,083 --> 00:41:30,887
and therefore this type ot unit is very suitable in climates
515
00:41:30,888 --> 00:41:34,090
where the winter temperature
falls below zero
516
00:41:34,358 --> 00:41:36,993
Again, where building code applies
517
00:41:37,261 --> 00:41:42,065
verify if you can install a glycol based system
518
00:41:42,299 --> 00:41:47,103
I onger pipe runs are possible since pumps can be added in the middle
519
00:41:47,471 --> 00:41:49,239
but it adds to the cost
520
00:41:49,240 --> 00:41:54,811
One condenser unit can feed multiple? CRAC units inside the data center
521
00:41:54,812 --> 00:41:59,082
and this is an advantage if there is a shortage of space
522
00:41:59,350 --> 00:42:05,989
But combining multiple CRAC units making use ot a single condenser
523
00:42:05,990 --> 00:42:11,294
results in that the same condenser to become a single point of failure
524
00:42:11,562 --> 00:42:13,730
So if the condenser fails
525
00:42:13,731 --> 00:42:17,166
it may take down multiple CRAC units
526
00:42:47,164 --> 00:42:47,564
Completed. Let's continue.
527
00:42:55,205 --> 00:43:00,810
Chilled water based systems provide a high efficiency rate within the data centra
528
00:43:01,078 --> 00:43:05,081
In a shared building where space is commonly used for office purpose
529
00:43:05,082 --> 00:43:08,484
it needs to be verified
if the building has the capability
530
00:43:08,485 --> 00:43:12,488
to supply enough chilled water to cool the data center
531
00:43:12,489 --> 00:43:15,725
Similar if maintenance or failure appears
532
00:43:15,726 --> 00:43:18,895
is the remaining level
of chilled water capable
533
00:43:19,163 --> 00:43:21,531
of supplying sufficient cooling capacity
534
00:43:21,532 --> 00:43:25,001
such that the data center will not suffer
535
00:43:25,269 --> 00:43:27,937
Building owners sometimes
charge on the amount
536
00:43:28,205 --> 00:43:31,107
of water measured in a unit or time frame
537
00:43:31,108 --> 00:43:35,378
and this may become an issue during the renewal ot the rental agreement
538
00:43:35,379 --> 00:43:37,780
whereby an increase of the water price
539
00:43:37,781 --> 00:43:41,718
may have a drastic impact on your operational cost
540
00:43:42,019 --> 00:43:47,323
Therefore contract terms and conditions need to be studied carefully
541
00:43:47,625 --> 00:43:50,760
In situations where you own the data center
542
00:43:50,761 --> 00:43:54,764
chilled water based systems come with a high initial cost
543
00:43:54,765 --> 00:44:00,637
and redundancy needs to be looked into as a result of a possible chiller failure
544
00:44:00,904 --> 00:44:03,806
Instead of using computer room air conditioners
545
00:44:03,807 --> 00:44:08,611
this system mates use of
computer room air handlers
546
00:44:08,879 --> 00:44:15,251
To provide cooling, an air handler uses chilled water and a control valve
547
00:44:15,252 --> 00:44:19,522
whereas an air conditioner uses refrigerant and a compressor
548
00:44:19,523 --> 00:44:24,293
This slide demonstrates the type of hybrid air conditioning system
549
00:44:24,294 --> 00:44:29,599
with a mixture ot a chilled water circuit and a direct expansion system
550
00:44:29,600 --> 00:44:34,971
The air conditioner unit is equipped with two evaporators in a single unit
551
00:44:35,205 --> 00:44:38,941
Under the normal conditions the chiller system is operating
552
00:44:38,942 --> 00:44:42,378
supplying cold water to the chilled water circuit
52985
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.