Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
00:00:00,033 --> 00:00:04,169
The computer room needs to be at least
260 centimeters or 8.5 feet in height
2
00:00:04,170 --> 00:00:05,037
The computer room needs to be at least
260 centimeters or 8 5 feet in height
3
00:00:05,038 --> 00:00:09,808
measured from the top of the raised floor to the bottom of the suspended ceiling,
4
00:00:19,119 --> 00:00:19,752
then additional height needs to be Icatered for in the computer room
5
00:00:19,753 --> 00:00:24,156
then additional height needs to be catered for in the computer room
6
00:00:35,335 --> 00:00:39,304
So, if you have a raised floor of forty centimeters,
7
00:00:39,305 --> 00:00:44,610
the area above the suspended ceiling should be at least sixty centimeters,
8
00:00:44,611 --> 00:00:45,077
but ideally, eighty centimeters in height
9
00:00:45,478 --> 00:00:47,713
but ideally, eighty centimeters in height
10
00:00:47,747 --> 00:00:48,614
but ideally eighty entimeters in height
11
00:00:48,615 --> 00:00:51,517
If the raised floor is sixty centimeters,
12
00:00:51,518 --> 00:00:56,588
the area above the suspended ceiling should be at least ninety centimeters,
13
00:01:03,229 --> 00:01:09,334
you have learned that various standards
apply to the raised access flooring system
14
00:01:09,335 --> 00:01:10,936
and that the UK PSA MOB is one of the most often used standards
15
00:01:14,240 --> 00:01:14,740
and that the UK PSA MOB is one lot the most often used standards
16
00:01:20,480 --> 00:01:25,818
since floor tiles are a part of a raised floor, different floor loadings may apply,
17
00:01:25,819 --> 00:01:27,019
such as uniform distributed loads, point loads or rolling loads.
18
00:01:29,155 --> 00:01:31,924
such as uniform distributed loads
point loads or rolling loads
19
00:01:43,369 --> 00:01:47,339
being the raised floor, the computer room and the suspended ceiling,
20
00:01:47,340 --> 00:01:50,642
and that appropriate
clearance must be present below
21
00:01:55,348 --> 00:01:59,885
Suspended ceilings create a nice-looking
computer room environment
22
00:01:59,886 --> 00:02:04,957
but it needs to be sized appropriately,
and similar to the raised floor,
23
00:04:15,221 --> 00:04:20,292
In the old days, light intensity used
be measured in a unit called Lumen
24
00:04:25,365 --> 00:04:25,931
Nowadays, the preferred measure of unit for light intensity is called Lux
25
00:04:52,992 --> 00:04:56,461
or three feet above the floor level.
26
00:04:56,462 --> 00:04:59,665
There are various standards available
27
00:05:02,302 --> 00:05:02,834
which address the light infrastructure in buildings.
28
00:05:10,543 --> 00:05:15,881
Ideally, therefore, you discuss with local consultants during the design phase,
29
00:05:15,882 --> 00:05:21,953
| to understand in which category computer room should be classified,
30
00:05:29,429 --> 00:05:35,534
that occupied spaces should have minimum light intensity of 500 Lux
31
00:05:35,535 --> 00:05:38,537
This is quite a high level, which is to ensure a safe working environment
32
00:05:39,105 --> 00:05:40,038
This is quite a high level, which is to ensure a safe working environment
33
00:05:58,124 --> 00:06:03,462
will ensure you still have appropriate light within the back of the rack itself,
34
00:06:08,768 --> 00:06:10,669
such as making
connections to the equipment
35
00:06:15,708 --> 00:06:18,610
by looking at the purpose of the room
36
00:06:34,494 --> 00:06:35,394
and in practice, this is 50 to 100 Lux
37
00:07:03,556 --> 00:07:09,728
Sufficient light levels must be present, 500 Lux in the horizontal plane,
38
00:07:23,543 --> 00:07:25,644
demonstrates some of the better choices,
39
00:07:25,645 --> 00:07:29,080
since for these light
fixtures the fluorescent
40
00:07:29,348 --> 00:07:32,818
tube is protected by a grill or plexiglass
41
00:07:36,489 --> 00:07:37,489
The bottom illustration shows
an example of an open light fixture,
42
00:07:37,924 --> 00:07:43,762
which is certainly not recommended, due to the possible damage that may occur
43
00:08:01,581 --> 00:08:07,686
to ensure that an equal level of light
is available throughout all aisles
44
00:08:07,954 --> 00:08:14,326
In some cases, where for example an office space is converted into a computer room,
45
00:08:14,327 --> 00:08:17,796
it sometimes results in misalignment
46
00:08:19,131 --> 00:08:20,565
Therefore, when you retrofit office area into a computer room,
47
00:08:21,133 --> 00:08:22,701
Therefore, when you retrofit an office area into a computer room,
48
00:08:23,102 --> 00:08:28,173
make sure that the contractor is realigning the light fixtures.
49
00:08:33,746 --> 00:08:37,482
which is also feeding ICT equipment
50
00:08:37,750 --> 00:08:43,054
Although it is tempting to make sure that there is always light in the data center,
51
00:08:49,562 --> 00:08:50,295
The issue is that fluorescent lights create a lot of harmonic distortion.
52
00:08:54,133 --> 00:08:54,533
The issue is that fluorescent lights create a lot of harmonic distortion,
53
00:08:58,237 --> 00:09:00,906
will create a power qualrty disturbances
54
00:09:00,907 --> 00:09:05,143
which could impact
the connected ICT equipment
55
00:09:05,144 --> 00:09:06,177
Therefore, lights must be connected
to the raw supply of the building,
56
00:09:09,515 --> 00:09:10,215
Therefore, lights must be connected
to the raw supply of the building
57
00:09:10,216 --> 00:09:15,554
and ideally, to the raw supply which is backed up by the standby generator
58
00:09:19,559 --> 00:09:25,130
you need to make sure that the lights
are connected to a dedicated UPS supply,
59
00:09:28,968 --> 00:09:29,834
instead of the UPS
that feeds the ICT equipment
60
00:11:08,134 --> 00:11:08,566
It is important to realize that most
regulations discussing emergency lights
61
00:11:13,539 --> 00:11:14,172
it is important to realize that most regulations discussing emergency lights
62
00:12:17,236 --> 00:12:20,138
and also higher intensity emergency lights
63
00:14:26,432 --> 00:14:30,969
perhaps you have a few leftovers
from that period in your life
64
00:14:36,508 --> 00:14:40,245
and the most common types are displayed on this slide
65
00:14:40,779 --> 00:14:45,583
The one at the too is sometimes referred
to as "the headlight emergency light”,
66
00:16:09,969 --> 00:16:14,172
This is certainly not a desirable.
especially when you have many lights
67
00:16:31,924 --> 00:16:36,794
and you will be shocked doing so yourself,
finding out that plenty of these lights
68
00:16:57,483 --> 00:16:58,883
This is achieved bv usina an EPS.
which is short for Emergency Power Supply
69
00:17:02,221 --> 00:17:02,653
This is achieved by using an EPS, which is short for Emergency Power Supply
70
00:17:03,355 --> 00:17:04,022
high is short for Emergency Power Si
71
00:17:25,144 --> 00:17:31,249
When the UPS has power on the input.
it will also have power on the
72
00:18:02,614 --> 00:18:05,550
only then the EPS will turn on the output,
73
00:18:10,355 --> 00:18:11,089
In some cases.
74
00:18:17,229 --> 00:18:22,033
In that case, the EPS
will be configured similar to the UPS,
75
00:19:50,455 --> 00:19:56,327
Lights should be adequately placed, taking into account potential obstructions,
76
00:20:28,227 --> 00:20:30,328
When designing emergency lights
77
00:22:07,392 --> 00:22:08,192
Studies from many hardware manufacturers Hand power consultants indicate
78
00:22:08,193 --> 00:22:13,497
Studies from many hardware manufacturers
and power consultants indicate
79
00:22:13,498 --> 00:22:18,836
that the quality of power supply to computer rooms is not always appropriate
80
00:22:19,371 --> 00:22:23,874
This may result in all sorts of
problems, such as failures on equipment
81
00:22:35,620 --> 00:22:41,992
Sometimes end-users spend a lot of time trying
to diagnose why the equipment is failing
82
00:23:00,045 --> 00:23:06,417
Unfortunately, a UPS is not able to address all potential power quality issues
83
00:23:18,363 --> 00:23:23,968
| As a result, if the ground quality at the input of the UPS is of poor quality
84
00:23:36,715 --> 00:23:39,917
as more ICT equipment is being deployed
85
00:23:58,804 --> 00:24:04,375
B Nevertheless, the current trend is that jnsity in terms of power per square meter
86
00:24:14,719 --> 00:24:16,854
which is the difference between the intake
87
00:24:24,863 --> 00:24:30,734
This slide demonstrates a simplified overview on how power is being distributed
88
00:24:43,482 --> 00:24:49,587
From this power generation plant, energy is distributed over transmission towers,
89
00:25:24,990 --> 00:25:29,527
eight hundred thousand volts is
stepped down to thirty three thousand volts
90
00:25:57,188 --> 00:26:00,090
to avoid the stepping down of the voltage
91
00:26:47,439 --> 00:26:49,840
This would commercially become unfeasible,
92
00:27:23,608 --> 00:27:26,276
and therefore it is not an option either
93
00:27:31,416 --> 00:27:32,316
to have a cost effective distribution
94
00:27:32,684 --> 00:27:33,851
to have a cost effective distribution,
95
00:28:03,682 --> 00:28:04,782
of how power is commonly distributed
96
00:28:04,783 --> 00:28:05,282
from the incoming power
supply to the computer room floor
97
00:28:06,184 --> 00:28:06,650
from the incoming power supply to the computer room floor
98
00:28:06,951 --> 00:28:08,519
from the incoming power
supply to the computer room floor
99
00:28:11,456 --> 00:28:12,956
we have left out details, such as breakers
and electrical distribution boards,
100
00:28:12,957 --> 00:28:16,226
we have left out details, such as breakers
and electrical distribution boards
101
00:28:16,227 --> 00:28:17,227
also called power distribution units,
102
00:28:18,897 --> 00:28:21,532
which are shortly referred to as PDU
103
00:28:26,071 --> 00:28:29,239
In case utility power becomes unavailable,
104
00:28:29,240 --> 00:28:34,044
for whatever reason, the standby generator is present, which can take over
105
00:28:43,922 --> 00:28:46,290
will detect this and start the generator
106
00:28:54,532 --> 00:29:00,370
are connected to an ATS panel, the Automatic Transfer Switch.
107
00:29:06,478 --> 00:29:10,481
or the emergency standby generator source
108
00:29:10,749 --> 00:29:13,383
As mentioned during the previous slide,
109
00:29:13,384 --> 00:29:20,057
the ATS panel will take power from either the utility power or the standby generator
110
00:29:46,885 --> 00:29:52,456
If the utility input fails, it means you have to switch from normal to emergency
111
00:29:58,630 --> 00:30:01,265
and moves to E to make a connection
112
00:30:05,737 --> 00:30:08,705
before it makes the connection with E
113
00:30:14,279 --> 00:30:18,715
Because of the break-before-make event, there will be a short moment
114
00:30:33,198 --> 00:30:39,036
However, other load which is connected, such as air conditioners and lights,
115
00:30:39,037 --> 00:30:44,341
might experience a small interruption of fifty to one hundred milliseconds
116
00:30:44,843 --> 00:30:49,913
This may cause the lights to flicker and air conditioners to turn off and restart,
117
00:30:50,715 --> 00:30:53,684
it is therefore recommended that air conditioners are configured
118
00:30:59,224 --> 00:31:03,227
Looking at the ATS types, in the middle and the right hand side on the slide,
119
00:31:03,228 --> 00:31:05,863
these are working on the same principle,
120
00:31:05,864 --> 00:31:11,735
but instead of having a rotor switching
from normal to emergency supply,
121
00:31:11,736 --> 00:31:16,506
it is now achieved by using
electromechanically activated breakers.
122
00:31:30,088 --> 00:31:32,990
such as the ATS panel and the UPS
123
00:31:43,401 --> 00:31:49,773
and during that time the UPS may need to be switched to the manual bypass mode
124
00:32:04,122 --> 00:32:10,227
For this reason, some data centers implement
a parallel configuration for the UPS
125
00:32:14,232 --> 00:32:18,502
It means that the two UPS systems are operating concurrently,
126
00:32:20,872 --> 00:32:26,743
Each UPS will take fifty percent capacity of the load inside the computer room
127
00:32:26,978 --> 00:32:27,577
Should one of the UPS systems fail or taken out of service
128
00:32:31,783 --> 00:32:36,286
due to maintenance, then the surviving UPS will take over the load
129
00:32:36,287 --> 00:32:40,791
and the data center continues to operate with full power protection
130
00:33:16,861 --> 00:33:18,261
such as a single generator serving as a backup to either source Aor B
131
00:33:20,698 --> 00:33:22,366
It is possible that instead of having adundant UPS systems in each feed,
132
00:33:22,367 --> 00:33:26,036
It is possible that instead of having
redundant UPS systems in each feed,
133
00:33:26,037 --> 00:33:29,239
the data center installs one UPS system,
134
00:33:32,176 --> 00:33:37,814
based on the assumption that either A or B or both feeds are active
135
00:33:38,316 --> 00:33:44,421
Since most ICT equipment is nowadays
equipped with an A and B power supply,
136
00:33:48,192 --> 00:33:52,529
However, there is still some equipment
that only have one power supply
137
00:33:52,530 --> 00:33:52,929
However, there is still some equipment that only have one power supply.
138
00:34:04,142 --> 00:34:10,514
To avoid this issue, most data centers will deploy a static transfer switch,
139
00:34:22,994 --> 00:34:23,460
but there is a fundamental difference between the ATS and STS,
140
00:34:28,700 --> 00:34:30,400
which I will discuss on the next slide
141
00:34:38,643 --> 00:34:39,743
This means that on the output of the STS there will be a break
142
00:34:40,611 --> 00:34:41,411
This means that on the output
of the STS there will be a break
143
00:34:42,980 --> 00:34:48,819
However, this break is very short, this since an STS is based on power transistors,
144
00:34:53,825 --> 00:34:57,294
An STS switches under twenty milliseconds.
145
00:35:05,036 --> 00:35:05,535
With power transistors in place, you are able to switch so fast
146
00:35:05,870 --> 00:35:06,603
With power transistors in place.
you are able to switch so fast
147
00:35:07,004 --> 00:35:09,940
With power transistors in place, you are able to switch so fast
148
00:35:29,460 --> 00:35:35,332
that these curves allow a power interruption on ICT equipment of twenty milliseconds,
149
00:35:39,570 --> 00:35:45,408
Anything more than twenty milliseconds may cause the ICT equipment to fail
150
00:36:03,794 --> 00:36:08,865
STS panels can come as large units, feeding an entire computer room,
151
00:36:08,866 --> 00:36:15,505
or a small rack mount unit, capable of switching power just for a single rack
152
00:36:16,040 --> 00:36:20,043
Notice there are intelligent STS devices in the market
153
00:36:26,050 --> 00:36:26,683
and if they are in sync, the system
will perform a make-before-break
154
00:36:33,324 --> 00:36:38,929
However, if the system measures
that the A and B source are not in sync
155
00:36:42,667 --> 00:36:47,971
to make sure that the two non-synchronous power sources are connected together,
156
00:36:53,778 --> 00:36:54,411
Therefore, the principle of
break before make is required
157
00:36:57,548 --> 00:37:00,684
when operating non-synchronous sources.
158
00:37:01,219 --> 00:37:07,057
The diagram on this slide represents another option for a dual feed setup,
159
00:37:10,127 --> 00:37:13,129
The advantage of this setup is that each feed will always be on,
160
00:37:14,265 --> 00:37:15,065
The advantage of this setup is hat each feed will always be on
161
00:37:15,066 --> 00:37:20,403
since it will take power from either the main incoming feed or the alternative feed
162
00:37:22,773 --> 00:37:27,577
the power feeds in the computer room
would be in an A+B configuration
163
00:37:28,346 --> 00:37:34,184
Depending on maintenance or a fault, the setup could automatically change to an A+A,
164
00:37:38,489 --> 00:37:43,293
There is no need to pull a separate power cable for the single cord equipment,
165
00:37:49,634 --> 00:37:54,704
As you can imagine, the cost to build and the cost to operate will increase.
166
00:38:10,988 --> 00:38:15,492
in addition, where single powei
luipment is still being used
167
00:38:52,163 --> 00:38:54,798
and some high level redundancy options
168
00:39:02,239 --> 00:39:05,442
it is commonly based on three phase power,
169
00:39:34,905 --> 00:39:37,874
Commonly, the cables are colour coded,
170
00:39:38,142 --> 00:39:44,514
The colour scheme varies by region or country, and in some cases even per timeline
171
00:39:49,019 --> 00:39:54,858
and therefore multiple colour schemes are potentially available in a single building
172
00:39:55,393 --> 00:39:59,929
This could lead to confusion.
and even dangerous situations
173
00:40:00,197 --> 00:40:06,035
if the people involved are not fully aware of the various colour coding schemes,
174
00:40:06,604 --> 00:40:12,675
Licensed electricians should be
familiar, so make sure qualified personnel
175
00:40:12,676 --> 00:40:15,879
is working on your electrical installation
176
00:40:22,820 --> 00:40:28,691
Therefore, you need to convert the incoming three phase power into single phase power
177
00:40:47,511 --> 00:40:53,349
Be aware that in some countries, single phase power is based on two wires only
178
00:41:14,839 --> 00:41:19,375
After the single phase breakers, you )mbine the ground and the neutral wire
179
00:41:27,651 --> 00:41:33,523
As you can see. the so-called
conversion from three phase to single phase
180
00:41:41,165 --> 00:41:46,503
| There are five wires: the neutral, which is commonly black, the ground, which is green,
181
00:41:54,745 --> 00:41:57,981
j To create a single phase using L1, it is combined with the neutral and the ground,
182
00:41:58,582 --> 00:41:59,782
To create a single phase using L1, it is combined with the neutral and the ground
183
00:42:16,066 --> 00:42:19,235
and you have created the single phase L2
184
00:42:43,494 --> 00:42:44,294
At the incoming part of the PDU
there is a three phase breaker installed
185
00:42:50,601 --> 00:42:56,673
with each of them having single phase breakers serving one of the three phases
186
00:43:04,148 --> 00:43:10,253
in order to create a single phase
supply, to which you can connect the load
187
00:43:21,432 --> 00:43:21,965
The output of the UPS is connected to he POU systems in the computer room,
188
00:43:31,342 --> 00:43:34,477
will now be connected to either phase one,
189
00:43:48,592 --> 00:43:54,697
and this means that each single phase should ideally cany the exact same load
190
00:44:12,249 --> 00:44:17,453
which the computer room floor manager
and his or her team need to take care of
191
00:44:17,454 --> 00:44:17,854
which the computer room floor manager and his or her team need to take care of
192
00:45:05,436 --> 00:45:11,574
From the UPS system, three phase
cabling runs to the power distribution unit
193
00:45:13,777 --> 00:45:16,646
also called the distribution board or DB
194
00:45:19,049 --> 00:45:20,717
at this point three phase power is
being converted to single phase power
195
00:46:43,267 --> 00:46:44,066
The total load of the new ICT equipment is roughly 8 kilowatt
196
00:50:31,928 --> 00:50:37,500
This will create a Imitation, since equipment installed in a particular rack row
197
00:50:56,520 --> 00:50:57,219
It will therefore allow more flexibility to manage the data center.
198
00:50:57,254 --> 00:51:00,890
It will therefore allow more flexibility to manage the data center
199
00:51:01,425 --> 00:51:04,393
Connecting equipment can be done as such
200
00:51:22,412 --> 00:51:22,878
but it wil help you to manage the data center for many years to come.
201
00:52:20,670 --> 00:52:26,008
allowing you to balance the load between the phases within each rack itself
202
00:54:22,492 --> 00:54:25,160
which is equipped with a dual power supply
203
00:54:30,200 --> 00:54:37,106
Note there’s also equipment in the market
which has three or even more power supplies
204
00:55:02,432 --> 00:55:03,766
it is recommended to connect it to an STS,
205
00:56:06,963 --> 00:56:07,896
What happens if it is the other way around
206
00:57:37,353 --> 00:57:38,086
There are many ways to connect power to a rack
207
00:57:38,321 --> 00:57:39,087
There are many ways to
connect power to a rack.
208
00:57:39,422 --> 00:57:43,926
This slide and the following slides will demonstrate some of the options
209
00:57:48,731 --> 00:57:53,469
a Power Distribution Unit, and then onwards to the power rail of the rack
210
00:57:53,770 --> 00:58:00,142
In this case, you have a single power rail, so many single points of failure
211
00:58:03,079 --> 00:58:04,379
Even if dual power supply equipment is present,
212
00:58:04,380 --> 00:58:07,082
such as in the bottom part of this rack,
213
00:58:10,753 --> 00:58:15,824
Yes, it is possible to connect the second power supply to the power rail,
214
00:58:15,825 --> 00:58:19,962
so that the equipment is at least
protected from a power supply failure,
215
00:58:19,963 --> 00:58:20,596
so that the equipment is at least protected from a power supply failure.
216
00:58:28,571 --> 00:58:32,841
This slide shows a slightly better configuration,
217
00:58:35,512 --> 00:58:38,714
In this option, there are two power rails
218
00:58:42,418 --> 00:58:46,922
will be connected to either the left or the right hand side power rail
219
00:58:47,223 --> 00:58:52,261
The dual power supply equipment can be connected to both power rails
220
00:59:06,376 --> 00:59:09,011
due to, for example, a breaker trip.
221
00:59:09,012 --> 00:59:11,713
the system will continue to operate
222
00:59:26,095 --> 00:59:30,566
that although the system with the dual power supply is still operating,
223
00:59:30,833 --> 00:59:35,404
it can no longer be used due to the loss of network connectivity
224
00:59:35,905 --> 00:59:38,840
If there is any failure on the UPS
225
00:59:46,316 --> 00:59:52,421
In this option, the computer room has two utility power feeds, indicated with A and B
226
00:59:52,689 --> 00:59:56,658
This configuration wil significantly improve the redundancy,
227
00:59:56,659 --> 01:00:00,662
since there is no longer a single point of failure, looking at the UPS,
228
01:00:00,663 --> 01:00:03,565
the PDU and the utility power feeds
229
01:00:03,566 --> 01:00:08,337
Since most of the equipment is
based on a single power supply
230
01:00:08,338 --> 01:00:12,874
it will, however, not contribute
much to achieving high availability
231
01:00:15,545 --> 01:00:20,082
there is still power in the rack, but since the majority of the equipment
232
01:00:30,727 --> 01:00:32,861
In this case, both the utility A and B feed are connected to an STS
233
01:00:34,097 --> 01:00:35,998
In this case, both the utility A and feed are connected to an STS
234
01:00:41,604 --> 01:00:42,137
Should either the A or B feed fail
235
01:00:50,113 --> 01:00:55,183
Realise that the STS is a single pint of failure in this configuration,
236
01:00:57,720 --> 01:01:01,356
then all single-cord equipment that is connected will shut it down
237
01:01:01,824 --> 01:01:02,357
then all single-cord equipment that is connected will shut it down
238
01:01:02,625 --> 01:01:08,463
Some STS panels have a maintenance
bypass, which can be activated,
239
01:01:14,037 --> 01:01:19,608
so not really helpful for the availability of the equipment itself
240
01:01:23,079 --> 01:01:27,315
the dual power supply equipment is also connected to the STS,
241
01:01:27,316 --> 01:01:30,285
whereas there is in fact no need for it.
242
01:01:43,032 --> 01:01:48,070
prefer this configuration, where only the single power supply equipment
243
01:01:50,973 --> 01:01:52,808
All dual power supply equipment connects directly to a power rail
244
01:01:53,676 --> 01:01:54,876
All dual power supply equipment connects directly to a power rail
245
01:02:09,759 --> 01:02:10,625
it does require an extra power rail in the back of the rack.
246
01:02:13,029 --> 01:02:16,198
There are some common techniques used in data centers
247
01:02:16,199 --> 01:02:19,167
to increase availability of equipment
248
01:02:19,368 --> 01:02:22,337
Quite obvious, try to deploy systems
249
01:02:22,338 --> 01:02:26,007
with dual or triple power supply built in,
250
01:02:26,109 --> 01:02:26,541
and connect these two dedicated utility feeds
251
01:02:28,111 --> 01:02:29,745
and connect these two dedicated utility feeds
252
01:02:35,118 --> 01:02:37,452
so the starting point is to determine
253
01:02:37,453 --> 01:02:40,689
what the ICT system is used for
254
01:02:40,957 --> 01:02:43,859
Arguably, in commercial data centers
255
01:02:43,860 --> 01:02:46,528
this discussion may never take place,
256
01:02:49,465 --> 01:02:49,898
having a customer who is responsible for their own ICT.
257
01:02:51,601 --> 01:02:54,269
Nevertheless, as a commercial operator,
258
01:02:56,372 --> 01:02:59,040
in advising the best possible solution
259
01:03:03,279 --> 01:03:06,214
Carefully review the electrical diagram,
260
01:03:15,258 --> 01:03:18,193
which ones are connected to the UPS,
261
01:03:18,194 --> 01:03:23,231
and which ones are connected to the raw power supply of the building
262
01:03:23,766 --> 01:03:26,701
If the computer room has a raised floor,
263
01:03:37,480 --> 01:03:38,780
This will then automatically create some level of separation
264
01:03:44,520 --> 01:03:49,324
These are switches, which are placed around a single point of failure
265
01:03:53,830 --> 01:03:57,299
will allow you to bypass faulty equipment
266
01:03:57,567 --> 01:04:00,468
or equipment which requires maintenance
267
01:04:01,037 --> 01:04:06,074
Be aware that using wrap-around bypass switches at the UPS level,
268
01:04:06,342 --> 01:04:11,379
does mean that no more power conditioning takes place once activated
269
01:04:15,318 --> 01:04:20,388
in extraordinary circumstances
when bypassing a UPS
270
01:04:20,957 --> 01:04:27,562
Let's have a look at an example of a wrap-around bypass at the ATS level
271
01:04:29,966 --> 01:04:33,435
the utility feed runs through the ATS,
272
01:04:33,436 --> 01:04:36,638
and the power goes down
stream towards the load;
273
01:04:37,139 --> 01:04:39,307
During backup operations,
274
01:04:41,944 --> 01:04:47,282
the ATS fails over to the generator,
which will take over the load
275
01:04:47,783 --> 01:04:48,650
So what happens in the
scenario the ATS fails
276
01:04:51,520 --> 01:04:54,990
or needs to undergo urgent maintenance?
277
01:04:55,258 --> 01:05:00,061
In that scenario, the utility
power bypasses the ATS.
278
01:05:16,279 --> 01:05:20,815
the back up scenario will be that the generator feeds power to the load,
279
01:05:23,719 --> 01:05:26,922
Some of these scenarios look frightening,
280
01:05:30,927 --> 01:05:36,197
This since earlier I explained it is a break-before-make scenario,
281
01:05:36,198 --> 01:05:39,134
and the switching time is not fast enough
282
01:05:46,075 --> 01:05:48,977
you have your UPS systems installed,
283
01:05:53,516 --> 01:05:56,685
Use breakers as much as possible
284
01:05:56,686 --> 01:06:02,223
to create a proper isolation of various parts of the electrical system
285
01:06:06,228 --> 01:06:10,498
and do not share breakers
over multiple power rails or racks,
286
01:06:28,050 --> 01:06:32,821
require the primary side of the aker to be wired to a common bus.
287
01:06:32,822 --> 01:06:37,859
which means you would have to connect wires on a live powered bus
288
01:06:41,364 --> 01:06:47,168
since often it is not allowed to work on an electrical board which is energised
289
01:06:47,436 --> 01:06:50,638
It is however known that some contractors
290
01:06:50,639 --> 01:06:53,041
are sometimes willing to do it anyway,
291
01:06:53,275 --> 01:06:55,677
with the excuse that they did it before
292
01:06:55,678 --> 01:06:58,313
and that they will be careful in doing so,
293
01:07:13,996 --> 01:07:16,931
As part of proper data centre management,
294
01:07:16,932 --> 01:07:19,601
you need to perform regular load checks,
295
01:07:19,602 --> 01:07:22,504
and verify the presence of earth leakage
296
01:07:23,039 --> 01:07:25,206
Keep imbalance to a minimum
297
01:07:25,207 --> 01:07:25,740
and do not let it exceed 10-15%,
298
01:07:28,377 --> 01:07:31,312
to avoid creating power quality issues
299
01:08:01,710 --> 01:08:05,413
When you design the power infrastructure for the data center,
300
01:08:10,486 --> 01:08:11,753
this since the data center environment is a very dynamic place
301
01:08:12,054 --> 01:08:14,756
| this since the data center vironment is a very dynamic place
302
01:08:17,626 --> 01:08:21,896
you have the choice of having
the power infrastructure either overhead,
303
01:08:26,702 --> 01:08:30,171
Where the raised floor is used for the
purpose of cooling
304
01:08:30,172 --> 01:08:33,074
installing the
power cabling under the raised floor
305
01:08:33,075 --> 01:08:38,613
should be done such that it has no or very minimal impact on the air flow
306
01:08:39,148 --> 01:08:41,816
Another point to consider is the distance
307
01:08:49,258 --> 01:08:53,795
and the network cabling
is overhead, you have good separation
308
01:09:01,504 --> 01:09:04,405
you need to keep proper separation between the copper network cabling
309
01:09:05,741 --> 01:09:11,579
and power cabling to avoid electromagnetic
fields issues on the network cabling
310
01:09:12,114 --> 01:09:16,384
When installing both power and network cabling under the raised floor,
311
01:09:16,385 --> 01:09:20,355
most designers will position the network cable at the back of the rack
312
01:09:34,470 --> 01:09:37,939
or you can opt to use busbar trunking,
313
01:09:41,610 --> 01:09:47,215
Traditionally, data centers apply power cabling inside the computer room
314
01:09:47,483 --> 01:09:48,683
In this set-up, you have a power distribution board,
315
01:09:50,186 --> 01:09:50,652
In this set-up,
you have a power distribution board,
316
01:09:51,053 --> 01:09:51,452
In this set-up, you have a power distribution board,
317
01:09:51,453 --> 01:09:56,858
from which cables will run to the various locations within the computer room
318
01:10:01,363 --> 01:10:02,297
but it does not give you any flexibility
319
01:10:03,265 --> 01:10:03,998
but it does not give you any flexibility
320
01:10:04,533 --> 01:10:08,469
If you have designed for the cabling to be single phase for each rack,
321
01:10:36,966 --> 01:10:42,770
This often means a lengthy process of getting a few vendors to come to the site,
322
01:10:52,915 --> 01:10:54,182
which will then happen in a production data center,
323
01:10:59,555 --> 01:11:03,024
It is of course
possible to use a mix of power ratings,
324
01:11:08,097 --> 01:11:13,134
since you do not know what type of equipment you will deploy in the future
325
01:11:28,817 --> 01:11:31,719
if you choose for overhead distribution
326
01:11:44,533 --> 01:11:51,172
Alternatively, you may be able to take tiple single phases out of the busbar trunk.
327
01:11:51,173 --> 01:11:55,943
which is determined by the type of tap-off boxes that you use
328
01:12:02,051 --> 01:12:07,889
so this would give you a great flexibility
in changing or adding capacity,
329
01:12:08,190 --> 01:12:14,562
or to change from single to three-phase power to the rack, and of course vice versa
330
01:12:17,533 --> 01:12:18,399
Busbar trunking
is more expensive, so as a designer,
331
01:12:19,234 --> 01:12:19,667
Busbar trunking is more expensive, so as a designer,
332
01:12:19,668 --> 01:12:22,870
you need
to balance the budget with flexibility
333
01:12:23,105 --> 01:12:27,608
Do realise that they data center may operate 10-20 years,
334
01:12:27,609 --> 01:12:28,142
and that during that time you will for
sure get a lot of equipment chages
335
01:12:32,681 --> 01:12:37,719
It is therefore a good idea to design for a flexible power infrastructure,
336
01:12:40,089 --> 01:12:42,824
since it will easily outweigh the hassle
337
01:12:43,325 --> 01:12:44,592
and additional
costs that you may incur in the future
338
01:12:44,993 --> 01:12:45,960
and additional costs that you may incur in the future
339
01:12:46,562 --> 01:12:51,366
if you have to change the traditional power cabling infrastructure a number of times,
340
01:12:51,367 --> 01:12:54,802
due to changes in the ICT equipment
341
01:12:55,571 --> 01:13:00,341
This slide demonstrates
the internal workings of the busbar trunk
342
01:13:01,543 --> 01:13:06,481
As you can see. the busbar trunk
is in fact a fully enclosed cable trunk
343
01:13:10,219 --> 01:13:13,621
which are based on all five wires being the ground,
344
01:13:17,092 --> 01:13:21,062
On top of the rail there
are openings, which are normally covered,
345
01:13:22,664 --> 01:13:27,969
and people cannot simply touch the actual power bars inside the trunk
346
01:13:41,016 --> 01:13:46,287
which ultimately determine what type of power is coming out of the tap-off box,
347
01:13:52,761 --> 01:13:53,561
In this configuration
the breakers are at the tap-off points,
348
01:13:55,564 --> 01:13:59,367
which means
that during an overload or short circuit,
349
01:14:03,071 --> 01:14:08,643
So. the breaker is
now location-based instead of centralised.
350
01:14:17,986 --> 01:14:23,257
which can be connected to the network to measure, either local or remote,
351
01:14:23,258 --> 01:14:29,397
all electrical parameters at the tap-off point, and to monitor a power trip remotely,
352
01:14:32,334 --> 01:14:38,706
Most busbar systems in the market have a fixed spacing between the tap-off points
353
01:14:39,241 --> 01:14:42,944
This may result cable routing and management challenges,
354
01:14:43,245 --> 01:14:48,282
when the tap-off point distance is not matching the rack spacing distance,
355
01:14:50,452 --> 01:14:55,223
Some busbar systems have
the ability for mounting the tap off point
356
01:15:10,906 --> 01:15:14,609
or network
cabling through a data center building
357
01:15:15,177 --> 01:15:20,181
Trunking is commonly used to run the cables from the distribution board
358
01:15:22,584 --> 01:15:27,255
Sometimes cable trunks are also used for network and high power cabling,
359
01:15:27,589 --> 01:15:28,189
Sometimes cable trunks are also used for network and high power cabling,
360
01:15:28,190 --> 01:15:29,857
in situations
where cables need physical protection,
361
01:15:31,026 --> 01:15:31,926
in situations
where cables need physical protection,
362
01:15:31,927 --> 01:15:34,829
because they may run through public areas
363
01:15:38,834 --> 01:15:43,871
you should realise that the cabling is running through a full enclosure.
364
01:15:43,872 --> 01:15:47,375
which will
cause heat development within the trunk.
365
01:16:00,889 --> 01:16:05,960
you derate the power
rating down to 900 ampere maximum
366
01:16:06,762 --> 01:16:08,930
In most cases, this is not a problem,
367
01:16:09,331 --> 01:16:09,931
In most cases, this is not a problem.
368
01:16:09,932 --> 01:16:14,735
since you will hardy ever operate at
full power ratings in the data center,
369
01:16:20,576 --> 01:16:24,045
Trays are used for both network and power cabin
370
01:16:44,232 --> 01:16:45,199
such as in
transformer rooms or generator rooms
371
01:16:45,500 --> 01:16:45,967
such as in
ransformer rooms or Generator rooms
372
01:16:46,001 --> 01:16:47,668
such as in
transformer rooms or generator rooms
373
01:16:48,503 --> 01:16:52,740
Cable baskets are normally used for network cabling only
374
01:16:52,741 --> 01:16:58,312
Cable baskets can be installed under the raised floor or hanging from the ceiling
375
01:16:58,847 --> 01:17:03,884
These cable baskets are fairly lightweight and not extremely strong,
376
01:17:03,885 --> 01:17:08,122
and therefore network cabling is commonly the only cable
377
01:17:32,881 --> 01:17:37,118
The terms "grounding" and earthing" refer to the same principle.
378
01:18:07,482 --> 01:18:10,384
as explained in the raised floor module
379
01:18:29,538 --> 01:18:32,873
For the ICT equipment, you want the ground to be as noise-free as possible,
380
01:18:33,975 --> 01:18:34,809
For the ICT equipment, you want the ground to be as noise-free as possible,
381
01:18:39,881 --> 01:18:45,720
The best way to achieve this is by creating
a dedicated ground for the computer room
382
01:19:01,636 --> 01:19:06,407
causing noise on the ground, which therefore could end up in the data center
383
01:19:27,963 --> 01:19:31,132
and similar applies to other ground systems
384
01:19:37,305 --> 01:19:42,076
Since you are connecting to ground
only at the low impedance ground pits,
385
01:19:54,055 --> 01:19:57,892
you need to make sure that the ground resistance at the earth pit is low
386
01:19:57,893 --> 01:19:59,126
you need to make sure that the
ground resistance at the earth pit is low
387
01:20:06,835 --> 01:20:11,872
The ground resistance can be measured by your electrical contractor,
388
01:20:19,347 --> 01:20:25,719
As such, it is recommended to measure the ground resistance at least once a year
389
01:20:57,586 --> 01:20:58,252
the raised floor, distribution boards,
390
01:21:09,297 --> 01:21:14,902
fire alarm panels and any other metal objects that you can identify.
391
01:22:00,315 --> 01:22:04,285
Common Mode Noise, shortly known as CMN
392
01:22:07,722 --> 01:22:12,259
CMN is measured at the point where the ICT equipment is connected,
393
01:22:24,739 --> 01:22:28,442
then the maximum allowed voltage between ground and neutral
394
01:22:30,845 --> 01:22:33,781
Most of the ICT equipment manufacturers
395
01:22:48,430 --> 01:22:51,632
it could pose a risk in a variety of ways
396
01:23:00,909 --> 01:23:05,980
Secondly, if you violate the
maximum level set by the manufacturer,
397
01:23:15,290 --> 01:23:17,157
for power to the equipment
398
01:23:17,692 --> 01:23:22,730
In the building, you normally have a bonding point between the ground and the neutral
399
01:23:22,731 --> 01:23:25,666
directly after the building transformer
400
01:23:25,900 --> 01:23:29,403
Since there is a direct bond, between ground and neutral,
401
01:23:29,404 --> 01:23:32,306
at this point you will measure zero volt
402
01:23:35,243 --> 01:23:38,445
there will be a potential long run of cables through the building,
403
01:23:51,526 --> 01:23:54,428
When the current runs through a cable,
404
01:23:57,332 --> 01:24:02,403
and as a result the voltage between neutral and ground will increase,
405
01:24:17,652 --> 01:24:18,318
one option is to make sure that power loads are property balanced
406
01:24:29,531 --> 01:24:34,301
Theoretically, you can argue that you could force another bonding pc
407
01:24:48,917 --> 01:24:52,086
as it will create serious safety issues
408
01:25:03,298 --> 01:25:08,869
However, what is allowed and what you can do in an electrical installation,
409
01:25:08,870 --> 01:25:11,505
is simply putting another transformer
410
01:25:14,976 --> 01:25:19,713
and then after that transformer again
connect the ground to the neutral
411
01:25:22,917 --> 01:25:25,819
what is called an isolation transformer
412
01:25:26,087 --> 01:25:32,226
The principle of this type
of transformer is indicated on this slide
413
01:25:34,629 --> 01:25:37,564
at the primary side of the transformer,
414
01:25:40,468 --> 01:25:41,235
you have four wires coming in, being three live wires and the ground
415
01:25:42,103 --> 01:25:45,272
Syou have four wires coming inj ing three live wires and the ground
416
01:25:45,507 --> 01:25:48,175
On the secondary side of the transformer,
417
01:25:48,810 --> 01:25:50,377
being the output of the transformer
418
01:25:50,845 --> 01:25:57,217
you have the ground wire, the three live wires and the brand new neutral wire
419
01:25:57,519 --> 01:26:03,857
This neutral wire has nothing to do with the existing neutral wire in the building,
420
01:26:08,129 --> 01:26:15,035
between this new independent neutral and the ground as its the first bonding point
421
01:26:15,303 --> 01:26:15,836
Therefore, at this point the voltage between around and neutral is zero
422
01:26:16,271 --> 01:26:17,104
Therefore, at this point the voltage between ground and neutral is zero
423
01:26:17,639 --> 01:26:18,038
Therefore, at this point the voltage between ground and neutral is zero
424
01:26:18,673 --> 01:26:19,339
Therefore, at this point the voltage between around and neutral is zero
425
01:26:19,374 --> 01:26:20,874
Therefore, at this point the voltage between ground and neutral is zero
426
01:26:23,778 --> 01:26:29,650
the input transformer looks like a delta ■star and the output looks like a wye
427
01:26:29,918 --> 01:26:36,323
Therefore, the isolation transformer is often called a delta-wye transformer
428
01:26:41,129 --> 01:26:44,031
and does not do any voltage conversion,
429
01:26:44,032 --> 01:26:49,102
as for which you normally use transformers in electrical installations
430
01:27:03,184 --> 01:27:05,018
which is feeding the computer room
431
01:27:06,187 --> 01:27:09,423
The location of this centralised isolation transformer
432
01:27:09,524 --> 01:27:14,027
could be in the UPS room or
somewhere near the computer room
433
01:27:16,197 --> 01:27:20,667
you run the power cabling
to the various power distribution boards,
434
01:27:27,875 --> 01:27:32,646
since the longer the distance between this bonding point and the rack,
435
01:27:32,647 --> 01:27:38,252
the higher the voltage that could build
up between the neutral and the ground
436
01:27:43,291 --> 01:27:46,760
or IEEE as they are commonly known,
437
01:27:46,761 --> 01:27:52,065
recommends the distance between this bonding point and the ICT equipment
438
01:27:57,905 --> 01:28:03,477
Another option is to have an isolation transformer in every distribution board,
439
01:28:06,681 --> 01:28:09,449
The principal is based on the fact that the distribution boards
440
01:28:10,251 --> 01:28:10,684
The principal is based on the fact that the distribution boards
441
01:28:16,824 --> 01:28:22,095
Therefore, having the isolation transformer inside the distribution board
442
01:28:22,096 --> 01:28:26,066
will ensure that the ground to neutral
bonding point
443
01:28:26,067 --> 01:28:31,672
will be close to the ICT equipment, which the best possible location
444
01:28:41,015 --> 01:28:46,853
Distribution boards with a transformer built-in are also larger in size,
445
01:28:46,854 --> 01:28:49,790
potentially taking up too much space,
446
01:28:49,791 --> 01:28:54,328
which could have been
used for ICT equipment racks instead
447
01:28:54,862 --> 01:28:58,899
Designers, therefore,
need to review each individual case
448
01:28:59,901 --> 01:29:04,671
and strike the best balance
between optimum electrical performance
449
01:29:04,672 --> 01:29:07,874
versus space and cost considerations
450
01:29:19,821 --> 01:29:24,858
The connection is established
through use of the magnetic flux principle
451
01:29:25,126 --> 01:29:30,430
In addition to the reduction of common mode noise due to the new bonding point,
452
01:29:33,901 --> 01:29:35,168
this galvanic isolation also
achieves some limited noise filtering
453
01:29:36,771 --> 01:29:39,506
this galvanic isolation
achieves some limited noise filtering
454
01:29:40,007 --> 01:29:43,977
An issue which you need
to address in the data center environment,
455
01:29:48,249 --> 01:29:51,718
Harmonics are basically power disturbances.
456
01:30:09,771 --> 01:30:15,075
Therefore, you need to make sure that ■the transformer can handle the heat
457
01:30:15,076 --> 01:30:20,147
generated by these harmonics, and mis is addressed with the K-Factor.
458
01:30:20,681 --> 01:30:23,884
The higher the K-factor of a transformer
459
01:30:29,190 --> 01:30:35,829
In data centers, the recommendation is o use K-13 type of isolation transformers,
460
01:30:40,668 --> 01:30:44,871
especially when older legacy
equipment is still in operation.
461
01:30:48,843 --> 01:30:54,147
so some data centers are now opting for lower K-Factor transformers
462
01:30:54,682 --> 01:30:58,985
It is advised to discuss with your electrical consultant,
463
01:30:58,986 --> 01:31:05,325
to make sure you choose the right K-Factor rating for your data center environment
464
01:31:05,593 --> 01:31:09,329
In computer rooms with high harmonic content,
465
01:31:09,330 --> 01:31:15,969
you may want to consider upgrading the neutral wire to double the normal size.
466
01:31:23,678 --> 01:31:26,346
and therefore less voltage creation
467
01:31:31,919 --> 01:31:37,724
| if there are high neutral currents
is a result of harmonics and imbalance
468
01:32:00,948 --> 01:32:05,986
There are a number of international standards which apply to distribution boards
469
01:32:21,903 --> 01:32:26,973
then make sure that the boards are tested
and approved by the local authorities
470
01:33:12,153 --> 01:33:16,957
You can imagine that if something would
happen within the board, such as for example
471
01:33:49,457 --> 01:33:55,295
and therefore potentially the most damaging component should it develop a fault.
472
01:34:18,953 --> 01:34:20,754
and in this case, a breaker is a functional component
473
01:34:21,455 --> 01:34:22,689
and in this case, a breaker is a functional component
474
01:34:23,257 --> 01:34:29,562
Basically it means that each busbar and each breaker have its own compartment,
475
01:34:29,864 --> 01:34:33,033
so even when the breaker would explode,
476
01:34:45,279 --> 01:34:51,117
but now also the termination of each
functional component has a compartment
477
01:35:05,232 --> 01:35:11,071
This is the best option for mission-critical
high power distribution boards,
478
01:35:19,013 --> 01:35:25,418
Note that in some countries electrical code [dictates certain type of boards to be used,
479
01:35:26,153 --> 01:35:26,753
depending on the current
and voltage rating of an electrical board
480
01:36:26,580 --> 01:36:33,019
And in addition to this, there is also separation between all functional components
481
01:36:40,427 --> 01:36:46,299
but now also the termination of each
functional component has a compartment
482
01:37:05,419 --> 01:37:10,456
The right hand side shows an example of a cross section of such board
483
01:37:33,614 --> 01:37:36,516
between the various functional components,
484
01:37:39,720 --> 01:37:43,790
On the right hand side is a cross section lot a form factor four distribution board.
485
01:37:46,227 --> 01:37:48,528
The power cables connect to the breaker, ■but enters into a small compartment
486
01:37:49,029 --> 01:37:51,431
The power cables connect to the breaker, but enters into a smal compartment.
487
01:38:26,100 --> 01:38:26,833
However it does come with
a price and that needs to be justified
488
01:39:02,736 --> 01:39:06,205
UPS systems, air conditioners, generators,
489
01:39:15,749 --> 01:39:20,086
the first number indicates the level of protection against a physical objects,
490
01:39:20,087 --> 01:39:21,087
the second number indicates
the level of protection against liquids
491
01:39:42,943 --> 01:39:48,581
If equipment is going to be installed
outdoors, for example an outdoor generator set,
492
01:39:48,582 --> 01:39:49,148
then it will be exposed to rainfall, and
therefore a higher level of protection
493
01:39:52,353 --> 01:39:53,353
then it wil be exposed to rainfell, and (therefore a higher level of protection
494
01:40:13,040 --> 01:40:20,480
Anyone familiar with IP grades will however understand when yousaylP20/IP21
495
01:40:20,981 --> 01:40:26,586
The table on this slide shows the level of protection presented by the first number,
496
01:40:37,998 --> 01:40:43,336
the higher the number, the more protection is applied against physical objects
497
01:40:43,871 --> 01:40:46,239
Level 0 offers no protection.
498
01:41:01,989 --> 01:41:04,624
they require a higher level of protection
499
01:41:35,222 --> 01:41:39,192
to placing equipment either indoors or outdoors
500
01:41:39,460 --> 01:41:42,395
UPS systems are normally placed indoors,
501
01:42:23,871 --> 01:42:29,942
This slide provides a visualization of
how IP grades are practically being used,
502
01:42:41,655 --> 01:42:47,493
you already get a very good indication of what level of protection is being offered
503
01:44:00,033 --> 01:44:01,000
such as grounding and common mode noise.
504
01:44:16,116 --> 01:44:20,920
IEC is short for
International Electrotechnical Commission,
505
01:44:20,921 --> 01:44:27,293
and specifically for the US the NEC being short for the National Electrical Code
506
01:44:28,128 --> 01:44:31,297
Be aware that
the specifications in these standards
507
01:44:38,472 --> 01:44:41,374
Because of that, it is sometimes required
508
01:44:45,112 --> 01:44:47,546
than what is described in these norms
509
01:44:48,081 --> 01:44:51,250
A good example is the ground resistance,
510
01:44:55,756 --> 01:44:59,225
As you may recall, the recommendation is
511
01:44:59,226 --> 01:45:02,895
to have a ground resistance of less than 1 Ohm for the computer room,
512
01:45:09,069 --> 01:45:13,572
The standards indicate that the nominal voltage should be maintained
513
01:45:17,511 --> 01:45:21,013
For frequency the tolerance is much lower,
514
01:45:21,014 --> 01:45:24,450
being a maximum of 1 percent up or down
515
01:45:24,985 --> 01:45:30,823
Common mode noise is limited to
1 percent of the phase to neutral voltage
516
01:45:42,803 --> 01:45:46,272
and refers to non-linear loading factors,
517
01:45:46,506 --> 01:45:49,975
ICT equipment is such non-linear load
518
01:45:57,984 --> 01:46:03,322
In a perfect world, there is no distortion since the load would be a linear load,
519
01:46:03,323 --> 01:46:07,827
which means that the current drawn by the load will be in sync with the voltage,
520
01:46:10,731 --> 01:46:16,569
However, due to the switched mode power supplies which are used in computer systems,
521
01:46:34,721 --> 01:46:38,424
On this slide an example of linear loads,
522
01:46:48,769 --> 01:46:52,505
Now we have a look at non-linear loads,
523
01:46:52,506 --> 01:46:56,776
as a result of the switch mode
power supply in the computer system,
524
01:47:07,421 --> 01:47:14,059
So, the conclusion - harmonics
are disturbances in the electrical system.
525
01:47:26,373 --> 01:47:26,772
depending on the country you are operating your data center
526
01:47:32,712 --> 01:47:35,347
UPS and air conditioner equipment.
527
01:47:37,451 --> 01:47:39,885
the sine wave could be impacted such
528
01:47:43,590 --> 01:47:46,759
With harmonics being a very complex topic
529
01:47:46,760 --> 01:47:52,097
remember that harmonics in
an electrical installation are undesirable,
530
01:47:52,098 --> 01:47:55,267
since they cause more heat dissipation,
531
01:48:09,616 --> 01:48:13,619
Measurements are commonly conducted by consultant organisations
532
01:48:25,165 --> 01:48:25,798
could alsohave
a negative impact on the generator
533
01:48:26,299 --> 01:48:27,533
could also have a negative impact on the generator,
534
01:48:28,301 --> 01:48:29,768
which may require the generator to be oversized
535
01:48:30,136 --> 01:48:31,704
which may
require the generator to be oversized
536
01:48:32,205 --> 01:48:37,510
This is technically possible, but it can
turnout to be very costly in doing so
537
01:48:38,311 --> 01:48:43,916
To counter harmonics, consider the usaae of active or passive filters
538
01:48:47,888 --> 01:48:51,891
How do harmonics relate to the UPS?
539
01:48:52,158 --> 01:48:54,827
Depending on the technology used,
540
01:49:04,404 --> 01:49:07,907
The rectifier is the input stage of UPS,
541
01:49:08,108 --> 01:49:11,844
which is converting the incoming alternating current,
542
01:49:18,351 --> 01:49:20,586
In simple terms, it takes
the 50 or 60 hertz building power,
543
01:49:21,354 --> 01:49:22,488
and converts it into battery voltage, which is used inside the UPS
544
01:49:24,424 --> 01:49:24,990
and converts it into battery
voltage, which is used inside the UPS
545
01:49:25,358 --> 01:49:26,258
and converts it into battery voltage, which is used inside the UPS
546
01:49:47,213 --> 01:49:48,347
Simply said, out of a full sine wave
547
01:50:04,497 --> 01:50:09,535
less pulses means more energy needs to be absorbed during each pulse,
548
01:50:18,011 --> 01:50:18,644
a 6 pulse rectifier can cause
as much as 30 percent disturbance
549
01:50:42,068 --> 01:50:44,803
IGBT is shorty for Insulated Gate Bipolar Transistor,
550
01:50:45,805 --> 01:50:46,271
IGBT is short for Insulated Gate Bipolar Transistor,
551
01:50:46,573 --> 01:50:49,208
which is similar to a Thyristor rectifier,
552
01:50:52,412 --> 01:50:53,012
The IGBT rectifier will create1 less disturbance on the supply,
553
01:50:53,213 --> 01:50:53,612
The IGBT rectifier wil create less disturbance on the supply.
554
01:50:53,913 --> 01:50:57,182
The IGBT rectifier will create less disturbance on the supply,
555
01:50:59,819 --> 01:51:05,658
Again, the resulting effect of the high harmonic levels is the Generation of heat
556
01:51:15,769 --> 01:51:20,305
voltage should be within
10 percent tolerance of the nominal voltaqe,
557
01:51:20,306 --> 01:51:24,276
and the sine wave of the
voltage should not be disturbed too much,
558
01:51:27,180 --> 01:51:27,746
therefore take note of the limits mentioned on this slide
559
01:51:48,802 --> 01:51:52,504
This slide visualises the CBEMA curve.
560
01:51:52,505 --> 01:51:56,008
mostly called ITIC curve these days
561
01:51:56,509 --> 01:52:02,614
This curve indicates what voltage levels are acceptable for ICT equipment
562
01:52:03,149 --> 01:52:06,185
All manufacturers will comply to the CBEMA curve.
563
01:52:06,619 --> 01:52:07,186
which means that as long as you keep your voltage within this curve,
564
01:52:10,423 --> 01:52:10,856
which means that as long as you keep your voltage within this curve,
565
01:52:10,857 --> 01:52:16,428
equipment manufacturers will guarantee that the equipment operates as specified
566
01:52:21,701 --> 01:52:28,640
The 100% indicator represents the nominal
voltage as it is in a given country.
567
01:52:42,756 --> 01:52:48,026
is the zone in which the voltage needs to be. which feeds the ICT equipment
568
01:52:53,133 --> 01:52:58,971
If the supply voltage ends up in this zone,
the ICT equipment may get damaged
569
01:53:00,006 --> 01:53:05,077
The lower right hand zone Ted to as the "no damage region"
570
01:53:05,578 --> 01:53:08,781
If the supply voltage ends up in this zone,
571
01:53:08,782 --> 01:53:11,183
your system will most likely shutdown
572
01:53:15,155 --> 01:53:20,726
You may remember the explanation for the static transfer switch (STS) earlier in this module
573
01:53:20,994 --> 01:53:26,064
If there is a power interruption with a duration less than twenty milliseconds,
574
01:53:26,299 --> 01:53:28,667
the equipment will continue
to ooerate thanks to the CBEMA curve
575
01:53:29,202 --> 01:53:30,836
the equipment will continue
to operate thanks to the CBEMA curve
576
01:53:31,371 --> 01:53:34,039
If you look at the horizontal part of the graph,
577
01:53:36,142 --> 01:53:39,044
you can identify the twenty milliseconds,
578
01:53:39,045 --> 01:53:43,882
and even if the voltage is zero percent,
it is still in the green zone.
579
01:53:44,417 --> 01:53:49,721
But if the voltage is zero percent land it exceeds the twenty milliseconds,
580
01:53:49,722 --> 01:53:52,624
you end up in the "no damage region”,
581
01:53:52,625 --> 01:53:55,027
which causes your system to shutdown
582
01:54:04,103 --> 01:54:09,408
This is related to the standards, which indicates that voltage should be nominal
583
01:54:13,913 --> 01:54:16,582
Looking at the vertical part of the graph,
584
01:54:22,956 --> 01:54:26,658
the ICT equipment may not get affected,
585
01:54:26,659 --> 01:54:31,730
as long as the time is short enough for the equipment to handle the surge.
586
01:54:32,565 --> 01:54:37,035
If you have a need for understanding the
power quality going into the computer room
587
01:54:37,036 --> 01:54:39,972
you can make use of power quality meters
588
01:54:40,540 --> 01:54:41,106
Often this is being outsourced
to a third party company,
589
01:54:43,743 --> 01:54:44,776
Often this is being outsourced to a third party company,
590
01:54:44,777 --> 01:54:48,480
who are able to measure
the power going into the computer room,
591
01:54:48,481 --> 01:54:52,251
comparing it to
the requirements of the CBEMA curve
592
01:55:18,578 --> 01:55:20,979
So far we have discussed grounding,
593
01:55:30,223 --> 01:55:31,056
and the CBEMA curve, and these are all factors to consider
594
01:55:31,357 --> 01:55:35,827
Can you recal the preferred maximum Ohm's level in grounding,
595
01:55:36,095 --> 01:55:36,695
or the maximum voltage when mention Common Mode Noise?
596
01:55:37,931 --> 01:55:40,632
or the maximum voltage when mention Common Mode Noise?
597
01:55:48,875 --> 01:55:52,644
Okay, study these values for two reasons
61675
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.