Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:01,270 --> 00:00:03,410
(narrator) With a solid estimate in hand,
2
2
00:00:03,410 --> 00:00:07,290
now, let's adjust it for two real-world factors,
3
3
00:00:07,290 --> 00:00:09,443
productivity and availability.
4
4
00:00:11,100 --> 00:00:13,760
The raw estimate from the deliverable lead
5
5
00:00:13,760 --> 00:00:17,000
is pure "effort" time, and must be factored
6
6
00:00:17,000 --> 00:00:20,090
by productivity and availability to obtain
7
7
00:00:20,090 --> 00:00:21,963
the actual "duration" time.
8
8
00:00:23,300 --> 00:00:25,490
That is the duration is equal to the effort,
9
9
00:00:25,490 --> 00:00:27,560
divided by the productivity percentage,
10
10
00:00:27,560 --> 00:00:29,603
divided by the availability percentage.
11
11
00:00:31,218 --> 00:00:34,430
First, we factor the raw effort estimate
12
12
00:00:34,430 --> 00:00:35,880
by a productivity percentage.
13
13
00:00:37,336 --> 00:00:40,330
The reason for this is that no human being
14
14
00:00:40,330 --> 00:00:42,839
sustains 100% productivity.
15
15
00:00:42,839 --> 00:00:45,490
They need breaks, receive telephone calls,
16
16
00:00:45,490 --> 00:00:47,533
must take care of admin issues, etc.
17
17
00:00:48,960 --> 00:00:51,450
This productivity factor usually takes into account
18
18
00:00:51,450 --> 00:00:53,630
annual vacation time as well,
19
19
00:00:53,630 --> 00:00:56,740
particularly if the project is a year or more long.
20
20
00:00:56,740 --> 00:00:58,830
So individual personnel vacation does not
21
21
00:00:58,830 --> 00:01:01,060
have to be included in the schedule.
22
22
00:01:01,060 --> 00:01:02,870
The productivity factor handles it.
23
23
00:01:02,870 --> 00:01:04,420
It'll all come out in the wash.
24
24
00:01:05,690 --> 00:01:09,680
So, every organization, sometimes each department,
25
25
00:01:09,680 --> 00:01:12,356
should have a standard productivity factor,
26
26
00:01:12,356 --> 00:01:17,180
typically between 70% and 85%.
27
27
00:01:17,180 --> 00:01:18,510
And it can be less.
28
28
00:01:18,510 --> 00:01:20,793
For example, construction companies typically factor
29
29
00:01:20,793 --> 00:01:23,210
estimates for work done outside in the winter
30
30
00:01:23,210 --> 00:01:26,670
at 60% productivity, at least here in Canada,
31
31
00:01:26,670 --> 00:01:29,410
because people move more slowly when they are all dressed up
32
32
00:01:29,410 --> 00:01:30,243
in the cold.
33
33
00:01:32,010 --> 00:01:34,440
Then each human resource estimate must be divided by their
34
34
00:01:34,440 --> 00:01:38,473
productivity factor to get their realistic costed time.
35
35
00:01:39,410 --> 00:01:41,530
This is usually done in the spreadsheet estimate
36
36
00:01:41,530 --> 00:01:44,310
before entering into the Gantt chart tool.
37
37
00:01:44,310 --> 00:01:45,610
We'll see an example soon.
38
38
00:01:47,510 --> 00:01:50,620
Then, if personnel are not working on the deliverable
39
39
00:01:50,620 --> 00:01:53,330
full-time, we also factor the estimate
40
40
00:01:53,330 --> 00:01:55,563
by their availability percentage.
41
41
00:01:56,720 --> 00:01:59,340
Availability is usually entered into and factored
42
42
00:01:59,340 --> 00:02:01,110
by the Gantt chart tool.
43
43
00:02:01,110 --> 00:02:03,860
It can be included in the spreadsheet estimate as well.
44
44
00:02:04,960 --> 00:02:09,183
So, for example, if a resource is available 50% of the time,
45
45
00:02:09,183 --> 00:02:12,440
the tool will double the duration time.
46
46
00:02:12,440 --> 00:02:14,580
If only available 33% of the time,
47
47
00:02:14,580 --> 00:02:17,013
it will triple the duration, etc.
48
48
00:02:19,090 --> 00:02:22,360
Now we've included real-world productivity and availability
49
49
00:02:22,360 --> 00:02:25,580
factors, we have a good idea of how long the deliverable
50
50
00:02:25,580 --> 00:02:27,683
work will actually take.
4366
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.