Now let's look at the practical essentials
2
2
00:00:03,230 --> 00:00:05,470
of preparation of the most detailed description of the
3
3
00:00:05,470 --> 00:00:08,083
project scope, the requirements.
4
4
00:00:09,540 --> 00:00:11,870
The first work product you produce during planning
5
5
00:00:11,870 --> 00:00:13,343
are the requirements.
6
6
00:00:14,240 --> 00:00:16,680
Sometimes these are documented as the last step
7
7
00:00:16,680 --> 00:00:19,670
of initiation, however gathering requirements
8
8
00:00:19,670 --> 00:00:22,350
can be a fair amount of effort, so it's better
9
9
00:00:22,350 --> 00:00:24,370
if initiating is kept to the minimum,
10
10
00:00:24,370 --> 00:00:27,310
then a planning budget allocated, then the first step of
11
11
00:00:27,310 --> 00:00:30,093
planning being preparation of the requirements.
12
12
00:00:31,610 --> 00:00:35,480
The requirements are simply the detail behind the objective.
13
13
00:00:35,480 --> 00:00:39,440
All the functions, features, quantities, standards
14
14
00:00:39,440 --> 00:00:42,090
and other information the project result needs to meet
15
15
00:00:42,090 --> 00:00:45,180
the objective and the planning team needs to know
16
16
00:00:45,180 --> 00:00:47,453
to put together a full and accurate plan.
17
17
00:00:49,050 --> 00:00:52,070
Missing requirements is one of the most frequent causes
18
18
00:00:52,070 --> 00:00:55,000
of project problems so you want to make sure
19
19
00:00:55,000 --> 00:00:56,503
you do a complete job.
20
20
00:00:57,420 --> 00:01:00,410
For example, here's a quote from a report on a failed
21
21
00:01:00,410 --> 00:01:03,373
project that captures a very common situation,
22
22
00:01:04,407 --> 00:01:07,040
"It was a classic case of not getting the requirements
23
23
00:01:07,040 --> 00:01:09,250
sufficiently defined from the beginning.
24
24
00:01:09,250 --> 00:01:14,250
And so it required a continuous redefinition of requirements
25
25
00:01:14,560 --> 00:01:17,520
that had a cascading effect on what had already
26
26
00:01:17,520 --> 00:01:19,277
been designed and produced."
27
27
00:01:20,500 --> 00:01:22,183
170 million dollar blowup.
28
28
00:01:23,390 --> 00:01:25,400
This will sound familiar to many people
29
29
00:01:25,400 --> 00:01:27,620
that have worked on projects.
30
30
00:01:27,620 --> 00:01:30,550
Doing a good job on requirements gathering up front
31
31
00:01:30,550 --> 00:01:31,523
is the solution.
32
32
00:01:32,849 --> 00:01:37,310
At the same time, it is also possible to go too far.
33
33
00:01:37,310 --> 00:01:40,180
Sometime a project is seen as an opportunity to address
34
34
00:01:40,180 --> 00:01:43,810
all the problems an organization has, so it is loaded up
35
35
00:01:43,810 --> 00:01:46,853
far beyond the ability of one effort to solve.
36
36
00:01:48,000 --> 00:01:49,420
Here's a quote on a failed project
37
37
00:01:49,420 --> 00:01:51,313
that captures this common mistake.
38
38
00:01:52,237 --> 00:01:55,610
"We started with a big bang approach and put every
39
39
00:01:55,610 --> 00:01:58,060
possible requirement into the program,
40
40
00:01:58,060 --> 00:02:01,307
which made it very large and very complex."
41
41
00:02:02,330 --> 00:02:03,813
A one billion dollar blowup.
42
42
00:02:05,490 --> 00:02:06,520
This is one of the reasons
43
43
00:02:06,520 --> 00:02:08,850
the initiation stage is so helpful.
44
44
00:02:08,850 --> 00:02:12,310
If you define a specific need, agree a one sentence
45
45
00:02:12,310 --> 00:02:15,820
objective to meet that need and then keep requirements
46
46
00:02:15,820 --> 00:02:18,950
gathering to respond just to that objective,
47
47
00:02:18,950 --> 00:02:20,450
there is a much greater chance of defining
48
48
00:02:20,450 --> 00:02:23,200
a manageable size, efficient project
49
49
00:02:23,200 --> 00:02:24,950
that will do just what it needs to.
50
50
00:02:26,430 --> 00:02:29,840
So strike the right balance.
51
51
00:02:29,840 --> 00:02:33,810
Interview everyone and make sure you identify all the
52
52
00:02:33,810 --> 00:02:36,740
requirements required to meet the objective and will drive
53
53
00:02:36,740 --> 00:02:38,343
schedule and cost.
54
54
00:02:39,400 --> 00:02:42,030
But don't go beyond the objective and add requirements
55
55
00:02:42,030 --> 00:02:45,793
that should really be addressed by separate projects.