Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
00:00:05,120 --> 00:00:09,890
In this lesson, we're going to take a look at a couple of really quick little formulas that can be
2
00:00:10,280 --> 00:00:10,850
useful.
3
00:00:11,390 --> 00:00:17,330
And that is the work day function and the work days int function.
4
00:00:17,570 --> 00:00:22,220
So let's start out with the work days function now in the table at the top here.
5
00:00:22,310 --> 00:00:29,740
I have a list of tasks that need to be completed, and I also have the start date of those tasks.
6
00:00:29,750 --> 00:00:33,830
So maybe this is some kind of basis for a project plan.
7
00:00:34,760 --> 00:00:41,720
And in Column C, I've listed out the number of work days that each of these tasks is going to take.
8
00:00:42,410 --> 00:00:49,970
Now, when I say work days, I mean Monday to Friday, so excluding the weekends I want I want to work
9
00:00:49,970 --> 00:00:55,340
out is the finish date based on the work days and the start date.
10
00:00:56,090 --> 00:01:03,470
So the work day's formula will basically calculate five days after the start date, but it won't include
11
00:01:03,470 --> 00:01:05,990
any weekends in that calculation.
12
00:01:06,230 --> 00:01:08,000
So let's go to finish date.
13
00:01:08,390 --> 00:01:12,830
We're going to type in equals and we're going to use the work day function.
14
00:01:13,970 --> 00:01:20,780
Now we have three arguments here start date days, and then we have an optional argument of holidays
15
00:01:20,930 --> 00:01:27,080
because what you can also doing here is get the formula to exclude holiday days as well, so those won't
16
00:01:27,080 --> 00:01:31,880
be public holidays, Christmas Day, New Year's Day, Easter Monday, things like that.
17
00:01:32,030 --> 00:01:37,370
Now, in order to include the holidays, you need to have the holidays listed out somewhere so you can
18
00:01:37,370 --> 00:01:41,960
see that I have all of the holidays in the UK listed out in a little table.
19
00:01:42,200 --> 00:01:44,750
So the first argument here is the start date.
20
00:01:44,930 --> 00:01:49,820
So I have that listed in cell before comma days.
21
00:01:50,120 --> 00:01:53,480
So how many days is this task going to take?
22
00:01:54,170 --> 00:01:57,380
Well, this task is going to take five days.
23
00:01:57,710 --> 00:01:59,510
Now I could leave it just there.
24
00:01:59,540 --> 00:02:01,460
I could close the bracket and hit enter.
25
00:02:01,700 --> 00:02:05,510
And it's going to give me my finished day, excluding weekends.
26
00:02:06,320 --> 00:02:12,650
However, if I wanted to include holidays as well, let's double click to edit comma.
27
00:02:13,310 --> 00:02:15,770
I can then select the holiday dates.
28
00:02:16,370 --> 00:02:25,370
So that is this that will range just here and say, and then I can copy this formula down and I have
29
00:02:25,370 --> 00:02:26,480
my finished dates.
30
00:02:26,870 --> 00:02:29,960
So that is how the work day's function works.
31
00:02:30,770 --> 00:02:33,620
Now what about the work days int function?
32
00:02:34,100 --> 00:02:39,050
Well, let's delete our AB finished date just here and take a look at work days int.
33
00:02:39,920 --> 00:02:41,090
And it's this one just here.
34
00:02:41,090 --> 00:02:43,490
Sorry, work day dot intel.
35
00:02:43,790 --> 00:02:44,810
Let's double click.
36
00:02:45,680 --> 00:02:52,700
Now this is pretty much the same, but it takes into account international weekends and holidays.
37
00:02:53,000 --> 00:02:54,840
So the first argument is start date.
38
00:02:54,860 --> 00:02:56,870
So before, that's nice and easy.
39
00:02:57,290 --> 00:02:58,190
Number of days?
40
00:02:58,190 --> 00:03:00,650
Well, that is five comma.
41
00:03:01,250 --> 00:03:03,590
Now the third argument is weekend.
42
00:03:04,130 --> 00:03:11,180
So if you have weekends that start on a different day, so maybe your weekend isn't Saturday and Sunday
43
00:03:11,180 --> 00:03:12,260
in your location?
44
00:03:12,530 --> 00:03:14,750
I know in the Middle East and other places.
45
00:03:14,990 --> 00:03:17,330
Sunday and Monday tend to be the weekend.
46
00:03:17,720 --> 00:03:22,280
You can account for that by selecting different days for your weekend.
47
00:03:22,880 --> 00:03:25,250
So let's just do Sunday Monday for change.
48
00:03:25,670 --> 00:03:29,120
And then if I want to add in holidays, I can do that as well.
49
00:03:29,330 --> 00:03:32,960
So I might want to use these holiday dates again.
50
00:03:33,500 --> 00:03:37,550
Close the bracket and enter, and then I can copy that formula down.
51
00:03:38,010 --> 00:03:42,920
Once again, I'm going to get that little error because I'm not using all of the data, so let's to
52
00:03:42,950 --> 00:03:44,360
ignore error.
53
00:03:44,810 --> 00:03:48,290
So that's the difference between workdays and work days into.
5112
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.