Would you like to inspect the original subtitles? These are the user uploaded subtitles that are being translated:
1
1
00:00:01,080 --> 00:00:02,740
When you procure something,
2
2
00:00:02,740 --> 00:00:05,250
there are two potential kinds of contract
3
3
00:00:05,250 --> 00:00:09,303
you can put in place: Fixed Price and Cost Plus.
4
4
00:00:10,670 --> 00:00:13,593
The most common kind of contract is Fixed Price.
5
5
00:00:14,840 --> 00:00:16,290
These are best for contracts where
6
6
00:00:16,290 --> 00:00:21,290
the scope is very well defined and very unlikely to change.
7
7
00:00:22,810 --> 00:00:24,410
The parties agree on a price,
8
8
00:00:24,410 --> 00:00:27,170
then a contractor can make or lose money
9
9
00:00:27,170 --> 00:00:28,803
without impacting the buyer.
10
10
00:00:30,240 --> 00:00:33,890
But the downside is they also fix the scope,
11
11
00:00:33,890 --> 00:00:35,630
so any changes to the scope are
12
12
00:00:35,630 --> 00:00:38,240
usually much more expensive since the
13
13
00:00:38,240 --> 00:00:41,023
contractor will then have all the leverage.
14
14
00:00:42,950 --> 00:00:44,570
And smaller companies will not be able
15
15
00:00:44,570 --> 00:00:47,030
to proceed if they are losing money.
16
16
00:00:47,030 --> 00:00:48,780
They will often just stop work and
17
17
00:00:48,780 --> 00:00:51,380
say "pay me more or sue me"
18
18
00:00:51,380 --> 00:00:54,313
even though it was supposedly Fixed Price.
19
19
00:00:55,990 --> 00:00:57,740
If the scope does change,
20
20
00:00:57,740 --> 00:00:59,070
remember one of the most important
21
21
00:00:59,070 --> 00:01:02,410
project management tricks of all, whenever possible,
22
22
00:01:02,410 --> 00:01:04,810
offset any additional work by removing
23
23
00:01:04,810 --> 00:01:08,430
some existing scope to balance off the impact.
24
24
00:01:08,430 --> 00:01:11,093
A win-win solution for everyone.
25
25
00:01:13,270 --> 00:01:16,393
The other main type of contract is Cost Plus.
26
26
00:01:17,350 --> 00:01:18,930
Cost Plus contracts are best for
27
27
00:01:18,930 --> 00:01:21,570
larger value and more complex efforts,
28
28
00:01:21,570 --> 00:01:24,180
where the scope will probably change,
29
29
00:01:24,180 --> 00:01:26,120
and arguing over changes in the price
30
30
00:01:26,120 --> 00:01:28,483
will likely cause many problems.
31
31
00:01:30,100 --> 00:01:32,290
Start by obtaining the best possible
32
32
00:01:32,290 --> 00:01:34,440
estimate of the work from the contractor,
33
33
00:01:34,440 --> 00:01:36,080
based on the requirements,
34
34
00:01:36,080 --> 00:01:37,810
often a full project plan,
35
35
00:01:37,810 --> 00:01:40,193
with as many assumptions as needed.
36
36
00:01:41,490 --> 00:01:44,280
Then, you agree to pay the contractor's cost,
37
37
00:01:44,280 --> 00:01:46,300
plus some preset profit percentage,
38
38
00:01:46,300 --> 00:01:47,520
often based on their bid rates
39
39
00:01:47,520 --> 00:01:49,950
for the various resources and materials,
40
40
00:01:49,950 --> 00:01:51,510
so then you know what the cost will be
41
41
00:01:51,510 --> 00:01:53,773
if you need more time or materials.
42
42
00:01:55,470 --> 00:01:57,440
You do need to do more project management
43
43
00:01:57,440 --> 00:01:59,560
of the contractor to maintain cost and
44
44
00:01:59,560 --> 00:02:02,403
schedule performance with Cost Plus engagements.
45
45
00:02:03,410 --> 00:02:06,230
So, integrate your and the contractor
46
46
00:02:06,230 --> 00:02:08,790
teams wherever possible setting up paired
47
47
00:02:08,790 --> 00:02:12,670
contacts and perhaps even colocate and
48
48
00:02:12,670 --> 00:02:15,560
implement very rigorous change control
49
49
00:02:15,560 --> 00:02:18,260
so you can actively manage any scope changes.
50
50
00:02:18,260 --> 00:02:19,280
So we'll take a look at this further
51
51
00:02:19,280 --> 00:02:21,180
in the monitoring and control chapter.
52
52
00:02:22,440 --> 00:02:26,193
Obtain written weekly and monthly reports on their progress,
53
53
00:02:27,200 --> 00:02:29,240
and put in checkpoints for formal notification
54
54
00:02:29,240 --> 00:02:30,960
by the contractor on their spending.
55
55
00:02:30,960 --> 00:02:35,150
For example, when they reach 25%, 50%, 75%, and 90%
56
56
00:02:35,150 --> 00:02:38,010
of their bid price guaranteeing you can catch
57
57
00:02:38,010 --> 00:02:40,313
cost issues if they are occurring.
58
58
00:02:42,418 --> 00:02:44,450
Then with Cost Plus contracts,
59
59
00:02:44,450 --> 00:02:46,090
if the scope does change,
60
60
00:02:46,090 --> 00:02:47,410
you'll be able to make the adjustments
61
61
00:02:47,410 --> 00:02:50,467
very quickly without a long contractual delay
62
62
00:02:50,467 --> 00:02:52,883
while you negotiate the increase.
5276
Can't find what you're looking for?
Get subtitles in any language from opensubtitles.com, and translate them here.